RERA registered projects in Bhayander West, Thane
37 projects are registered with MahaRERA in Bhayander West, Thane. Of the 21 still under construction, 6 have passed the completion date their builder declared to RERA.
15
Ongoing, on schedule
6
Ongoing, past due date
10
Completed
6
Lapsed or deregistered
More localities in Thane
Most active builders
- Grandbuild Land Developers LLP3
- A G Superstructures Private Limited3
- Shri Ratnaraj Infra LLP2
- Ritu Corp1
- Ark Realty1
- Vaibhav Siddhi Construction Co1
- Marvel Constructions1
- Vardhaman Builders1
All projects
Showing 1–37 of 37, newest registrations first.
- Windsor Tower CGrandbuild Land Developers LLPP51700081077OngoingMar 2032
- Windsor Tower BGrandbuild Land Developers LLPP51700081067OngoingMar 2032
- Windsor Tower AGrandbuild Land Developers LLPP51700081037OngoingMar 2032
- Tirupati Ritu EmpireRitu CorpP51700080735OngoingDec 2029
- Narmadalifestyle Building No 2 AntarikshArk RealtyP51700080185OngoingSept 2030
- Vaibhav Serenity - Wing DVaibhav Siddhi Construction CoP51700079779OngoingApr 2028
- Icon 101Marvel ConstructionsP51700078788OngoingDec 2029
- Vardhaman EnclaveVardhaman BuildersP51700076855In extensionDec 202612 months late
- Man MandirTritonia Buildcon and Infra Private LimitedP51700054203OngoingDec 2028
- Windermere Tower AA G Superstructures Private LimitedP51700052078OngoingDec 2028
- Windermere Tower CA G Superstrcutures Pvt LtdP51700050981OngoingDec 2028
- Windermere Tower BA G Superstructures Pvt LtdP51700050737OngoingDec 2028
- Skyline Wing - CShri Ratnaraj Infra LLPP51700050558OngoingDec 2029
- Skyline Wing - BShri Ratnaraj Infra LLPP51700050604OngoingDec 2029
- Windermere Building No 1 To 6A G Superstructures Pvt LtdP51700049440OngoingDec 2027
- Shree Jagannath TowerOmkar RealtorsP51700045506LapsedDec 2025
- Hema KunjBhadrankar Enterprises LLPP51700028739CompletedAug 2023
- Bhairav EnclaveLeena Estate VentureP51700028700OngoingAug 2026
- ChandanbalaP51700027814In extensionDec 202619 months late
- Imperial ResidencyLeena Construction Co.P51700026852In extensionJun 202712 months late
- Sudama Vallabh wing A,B,CP51700026698In extensionJun 202712 months late
- Om Ganesh KrupaP51700023861LapsedNov 2024
- Salasar Sparsh Phase IMaxus Prime Realty LLPP51700022775In extensionDec 20283.3 years late
- SnehamParidhi DevelopersP51700020410CompletedSept 2025
- Suvarna PlazaMahalaxmi Construction CoP51700020360CompletedDec 2025
- Bhakti ParkP51700019257LapsedDec 2022
- Anandam-BGeeta DevelopersP51700017941CompletedJun 2024
- MukundamShree Ramjeevdani RealtorsP51700017888In extensionAug 20273.0 years late
- Anandam-APahal Construction Co.P51700017515CompletedJun 2024
- Salasar New Sai Kripa Co-Operative Housing Society Ltd.Salasar RealtorsP51700016511CompletedDec 2022
- Radha KrishnaP51700016450CompletedDec 2022
- Venkatesh HeightsM/s Shree Balaji FoundationP51700012201CompletedDec 2021
- Saroj Chandra ResidencyAshtavinayak EnterprisesP51700011906LapsedDec 2025
- Ramdev VaayuP51700010095CompletedMar 2018
- New Yashodeep Co-Op. HSG. Soc. LtdH K ConstructionsP51700009673LapsedOct 2023
- Tirupati HeightsM/s Shri Tirupati RealtyP51700008762LapsedDec 2023
- Annapurna AquariusAnnapurna PropertiesP51800002185CompletedDec 2023