RERA registered projects in Ghansoli, Thane
64 projects are registered with MahaRERA in Ghansoli, Thane. Of the 20 still under construction, 3 have passed the completion date their builder declared to RERA.
17
Ongoing, on schedule
3
Ongoing, past due date
38
Completed
6
Lapsed or deregistered
More localities in Thane
Most active builders
- Aurum Realestate Developers Limited7
- Shivkrupa Enterprises2
- CIDCO of Maharashtra Ltd.2
- Savita Homemakers LLP2
- Geecee Ventures Limited2
- Infopark Developers Private Limited1
- Alliaance Infratech1
- Alliaance Gloria Lifespaces1
All projects
Showing 1–64 of 64, newest registrations first.
- Orbis Phase 1Infopark Developers Private LimitedPR1331012601575OngoingAug 2032
- Q Living R8Aurum Realestate Developers LimitedPR1330002601338OngoingDec 2030
- Alliaance LagunaAlliaance InfratechPM1330002600295OngoingMar 2030
- Alliaance GloriaAlliaance Gloria LifespacesPR1330002502624OngoingDec 2028
- Century ThreeM/s. Shubham DevelopersPM1330002502117OngoingDec 2028
- Leaf MountInfinity InfraPR1330002501806OngoingDec 2029
- Sadguru Shree Swami Samarth ResidencyShreesadguru Infrabuild LLPPR1330002501163OngoingMay 2029
- Gami TelonLal Gebi Infra Private LimitedP51700080035OngoingDec 2029
- The ElementsTPV Ventures LLPP51700079613OngoingDec 2031
- Krishna IrisGami and Krishna Enterprises LLPP51700079334OngoingDec 2028
- Juhi EleganceJuhi Habitat Pvt. Ltd.P51700079049OngoingDec 2030
- Alliaance the ViewAlliaance RealtyP51700078452OngoingDec 2030
- Gami Satyam SkyscapeGami and Satyam Ventures Private LimitedP51700078229OngoingDec 2030
- Century TwoCity InfraP51700053044OngoingMar 2028
- Shubham ResidencyShubham RealtyP51700052989LapsedJun 2025
- Neelkanth Palm AvenueNeelkanth InfratechP51700052959OngoingDec 2029
- Krishna HeightsMit InfraP51700051727OngoingMar 2028
- Diya HomesP51700049874CompletedDec 2023
- Kusum ResidencyP51700048955In extensionDec 20269 months late
- Somnath HeightsBhanushali and AssociatesP51700048050CompletedDec 2025
- Alliaance IconSatyam InfraP51700046173OngoingDec 2026
- Yashraj HeightsP51700034878CompletedJan 2025
- SpringsQueenstown Constructions Private LimitedP51700031471CompletedMar 2024
- Gami EvaThalia and Gami EnterprisesP51700031192CompletedJun 2023
- SairajP51700029720LapsedMar 2023
- Ganesh ApartmentGlobe DevelopersP51700027652CompletedNov 2022
- Pyramid IconTitanium InfraconP51700027223CompletedJun 2023
- Mahavir SapphireP51700025896CompletedJun 2024
- Shruti ApartmentP51700025732CompletedNov 2023
- Gami Asters A WingThalia and Gami EnterprisesP51700025311In extensionDec 20262.0 years late
- Bhakti ParkShivkrupa EnterprisesP51700024721CompletedMar 2023
- Pooja AnganSairaj ProjectsP51700024094LapsedDec 2022
- Q Islands R5Aurum Realestate Developers LimitedP51700023911LapsedDec 2025
- Q Islands R4Aurum Realestate Developers LimitedP51700023775CompletedDec 2024
- Rangvel ParkRangvel EnterprisesP51700023538CompletedDec 2022
- Chamunda DaffodilsChamunda Infrastructure LtdP51700023025CompletedDec 2023
- Asha HarmonyVir EnterprisesP51700022377CompletedDec 2022
- Neelkanth AlpineNeelkanth InfraconP51700021881CompletedJul 2024
- Bhakti PalaceShivkrupa EnterprisesP51700021884CompletedDec 2021
- Alliance OneAlliance InfraP51700021771CompletedJul 2024
- N G Grand Plaza Phase IIOm Namah Shivay Developers Private LimitedP51700021598LapsedSept 2019
- Satyam OrchidGirija InfrastructureP51700021026CompletedDec 2021
- Shakti AuraShakti DevelopersP51700019646LapsedJun 2023
- Krishna LilacAmbika EnterprisesP51700018014CompletedSept 2020
- Century OneM/s City InfraP51700017969CompletedMar 2023
- Krishna IconShree Hari RealtyP51700017537CompletedMay 2022
- Plot 1 Sector 10 GHANSOLICIDCO of Maharashtra Ltd.P51700017366CompletedJun 2021
- Plot 2 Sector Sector 10 GHANSOLICIDCO of Maharashtra Ltd.P51700017421CompletedSept 2022
- Q Residences R2 UAurum Realestate Developers LimitedP51700017305CompletedDec 2022
- Q Residences R3Aurum Realestate Developers LimitedP51700017304CompletedDec 2023
- Sai PalaceP51700016785CompletedJun 2022
- Payal PrideMit EnterprisesP51700016608CompletedMar 2022
- Mahaavir AnmolMahaavir ImpexP51700016378CompletedMar 2023
- Pinnacle ResidencyP51700016288CompletedSept 2020
- Goldcrest Residency - Phase 1Savita Homemakers LLPP51700012365CompletedDec 2020
- SunberryNeelkanth Infratech CoP51700011752CompletedDec 2023
- Goldcrest Residency - Phase 2Savita Homemakers LLPP51700010579In extensionMar 20275.8 years late
- Q Residences R2Aurum Realestate Developers LimitedP51700007844CompletedDec 2022
- Neelkanth SparkleNeelkanth EnterprisesP51700005915CompletedJun 2018
- MapleShreeji DevelopersP51700005148CompletedDec 2021
- Cloud 36-Phase IIGeecee Ventures LimitedP51700004872CompletedDec 2018
- Q Residences R1Aurum Realestate Developers LimitedP51700001722CompletedDec 2021
- Cloud 36 -Phase IGeecee Ventures LimitedP51700001178CompletedDec 2018
- Juhi SerenityP51700000074CompletedDec 2023