RERA registered projects in Badlapur West, Thane
63 projects are registered with MahaRERA in Badlapur West, Thane. Of the 22 still under construction, 3 have passed the completion date their builder declared to RERA.
19
Ongoing, on schedule
3
Ongoing, past due date
29
Completed
12
Lapsed or deregistered
More localities in Thane
Most active builders
- Pokhriyal and Associates3
- Shashwat Homes2
- Shree Vakratunda Builders & Developers2
- Shrushti Developers2
- Raj Superstructure1
- Town Icon1
- Thakur Construction1
- Koutilya Enterprises1
All projects
Showing 1–63 of 63, newest registrations first.
- Raj CornerstoneRaj SuperstructurePR1330002601601OngoingDec 2029
- Sudarshan ViharPR1330002601354OngoingDec 2029
- Om Sagar ParkTown IconPR1330002503014OngoingMar 2029
- Ranimaa Devi CHSThakur ConstructionPR1330002501812OngoingDec 2027
- Shiv-KutirKoutilya EnterprisesPR1330002501414OngoingDec 2029
- Jyoti Jagannath HeritageMayur GroupPM1330002501384OngoingDec 2029
- Samruddhi NXSai Samruddhi Avenue LLPP51700080387OngoingDec 2029
- Gurudev PalaceT and T DevelopersP51700079688OngoingJun 2028
- Shiv Sarovar Wing BP51700079043LapsedMay 2026
- Ganesh Villa CHSLBhavani EnterprisesP51700077491In extensionApr 202822 months late
- Swanand VedikaAtharv InfrastructuresP51700077350OngoingJun 2029
- Shreepal House Complex CHSLTulja Bhawani Builders and DevelopersP51700056459OngoingMay 2028
- Jay Ramdarshan CHS LtdMitra BuildconP51700055924OngoingNov 2026
- Sky Galaxy BLDG No 1Atree DevelopersP51700054404OngoingDec 2026
- Pokhriyal ParamountPokhriyal and AssociatesP51700053054OngoingDec 2028
- Shreeji Landmark Phase IShreeji BuildconP51700052093OngoingDec 2027
- Sonal ParadiseShubh GroupP51700051894OngoingDec 2026
- Lawate HeightsShree Ganesh DevelopersP51700051277CompletedMar 2026
- Nirman SignatureShree Sha DevelopersP51700050640CompletedMar 2026
- The Address Wing C Phase IIISadguru AssociateP51700050566OngoingDec 2026
- Mahalaxmi ResidencyYash InfraP51700050262LapsedJun 2025
- SHASHWAT PARK Z-5 A and B WING APARTMENTShashwat HomesP51700050263CompletedJun 2026
- Sairaj EmeraldSairaj EnterprisesP51700049097CompletedSept 2023
- Shivam Paradise Phase IM.K. EnterprisesP51700048453LapsedJun 2025
- Vatsala ResidencyVatsala Realtor and Developers LLPP51700048485In extensionApr 202718 months late
- P G TowerP G DevelopersP51700047914LapsedDec 2025
- Siddhi Vinayak Pooja Co Op HSG Soc LtdShree Siddhivinayak DevelopersP51700047803CompletedDec 2024
- Kalawati HeightsPrabha Builders and DevelopersP51700047127LapsedSept 2024
- Swapna Rekha CHSShree Sadguru HomesP51700046892LapsedJun 2026
- Green TouchShree Vakratunda Builders & DevelopersP51700046822OngoingDec 2027
- Shiv SarovarP51700045969LapsedMay 2025
- Deep PushpNeha ConstructionP51700034233CompletedDec 2024
- Green Touch Building No 2Shree Vakratunda Builders & DevelopersP51700033633LapsedDec 2025
- Shivam Greens Phase - II Wing - BM.k.developersP51700033032CompletedDec 2024
- Shivanjali HeightsShivanjali ConstructionP51700032585CompletedJun 2023
- Bhawani Shankar Heights Wing-CBhawani Shankar Builders & DevelopersP51700031599OngoingDec 2027
- Nirmala ParadisePokhriyal and AssociatesP51700030774CompletedSept 2024
- Satish Oak HeightShree Sai Prathamesh DevelopersP51700030403CompletedMar 2026
- Om AdityaP51700029570CompletedJul 2022
- Sadguru Symphony - Wing - A, D, E, F and G of Phase-IISadguru InfraP51700029442In extensionDec 20262.5 years late
- Hari SanskrutiSaraswati DevelopersP51700028855CompletedJun 2026
- Shrushti Aarambh - Wing A1, B and B1 of Phase - IIIShrushti DevelopersP51700027627LapsedOct 2024
- MahiNina DevelopersP51700027463CompletedJun 2025
- Sairaj AnnexAvs EnterprisesP51700027311CompletedSept 2022
- Umiya Complex Wing H and Wing GUmiya AssociatesP51700026865CompletedJun 2025
- Pinnacle RoyalPinnacle InfraP51700025265CompletedMar 2023
- Pokhriyal ParadisePokhriyal and AssociatesP51700023364LapsedOct 2022
- Shree ResidencyShree DevelopersP51700022360CompletedDec 2019
- Shree Ujwala GalaxyShree Shiv Om DevelopersP51700021402CompletedMar 2024
- Orient LegacyJewel OrientP51700021264LapsedJun 2025
- Metro Aangan Phase - IMetro CreatorsP51700020756OngoingDec 2028
- Balkrushna ArcadeP51700020212CompletedSept 2021
- Hari ShrushtiShiv Shakti DevelopersP51700020058CompletedDec 2022
- Gauri SankalpPatil SonsP51700018384CompletedJun 2022
- Redevelopment of Trimurti Co Operative Housing Ltd Wing A Wing B Wing C Phase 1Geetai InvestmentP51700018300CompletedMar 2022
- VandanamMetro BuildconP51700017022CompletedDec 2021
- Shivam HillsM.k.realtorsP51700016819CompletedNov 2020
- Badlapur ArcadeMahalaxmi Builders & DevelopersP51700015624CompletedDec 2023
- Shrushti Aarambh, Wing - C of Phase - IShrushti DevelopersP51700015554CompletedDec 2022
- Krishna C and D WingNina BuildersP51700015548CompletedDec 2021
- Trishul Golden VilleA Plus Life SpaceP51700015246CompletedDec 2022
- Evergreen Residency Wing A,b,d,eBalaji ConstructionP51700014719LapsedDec 2022
- Shashwat Park 1-ABShashwat HomesP51700014005CompletedMar 2022