Lapsed projects
MahaRERA lapsed projects
A MahaRERA registration lapses when the completion date the builder declared passes without a completion filing or an extension. These figures cover every lapsed and deregistered project in Maharashtra, and update as new filings are read.
As of 3 Nov 2026
8,669
Registrations lapsed
323
Projects deregistered by MahaRERA
18%
Of all 50,069 registrations, lapsed or deregistered
70
Lapsed in the last 90 days
34%
of lapsed projects had already been extended at least once (2,919 of 8,669).
1,03,976 units sold
out of 1,92,548 in the 2,249 lapsed projects whose filings list units, as filed by the builder before the registration lapsed.
What does "lapsed" mean on MahaRERA?
A MahaRERA registration is valid until the completion date the builder declared, plus any extension MahaRERA grants. When that date passes and the builder has filed neither a completion (occupancy) certificate nor an extension, the portal shows the project's status as Lapsed. Deregistered means MahaRERA cancelled the registration.
Lapsed doesn't always mean a stalled site: some projects are finished on the ground but the builder never filed for completion. To see where a project stands, search it on AskRera or open its district list below, filtered to lapsed projects, and check the latest filings and extension history.
Lapsed projects by district
| District | Registered | Lapsed | Share | Units sold in lapsed projects |
|---|---|---|---|---|
| Pune | 12,486 | 2,396 | 19% | 35,608 of 53,846 |
| Thane | 6,981 | 1,187 | 17% | 20,921 of 36,580 |
| Raigad | 5,414 | 1,076 | 20% | 8,564 of 23,373 |
| Mumbai Suburban | 6,351 | 1,006 | 16% | 17,370 of 29,536 |
| Nashik | 3,832 | 478 | 12% | 2,189 of 5,083 |
| Palghar | 2,722 | 420 | 15% | 3,956 of 6,910 |
| Nagpur | 2,531 | 343 | 14% | 4,228 of 10,124 |
| Aurangabad | 1,230 | 241 | 20% | 761 of 2,359 |
| Satara | 987 | 237 | 24% | 660 of 2,138 |
| Ratnagiri | 987 | 198 | 20% | 465 of 1,633 |
| Sangli | 740 | 183 | 25% | 488 of 1,054 |
| Solapur | 493 | 164 | 33% | 207 of 1,157 |
| Mumbai City | 721 | 138 | 19% | 2,417 of 4,464 |
| Kolhapur | 792 | 136 | 17% | 355 of 1,146 |
| Amravati | 380 | 89 | 23% | 109 of 782 |
| Sindhudurg | 440 | 79 | 18% | 748 of 2,056 |
| Ahmednagar | 418 | 71 | 17% | 201 of 456 |
Lapsed projects by locality
| Locality | Registered | Lapsed | Share |
|---|---|---|---|
| Panvel, Raigad | 356 | 68 | 19% |
| Chikhali, Pune | 182 | 45 | 25% |
| Badlapur, Thane | 186 | 36 | 19% |
| Ravet, Pune | 193 | 36 | 19% |
| Ambernath, Thane | 207 | 35 | 17% |
| Wagholi, Pune | 211 | 34 | 16% |
| Moshi, Pune | 162 | 33 | 20% |
| Baner, Pune | 259 | 33 | 13% |
| Kalyan, Thane | 196 | 32 | 16% |
| Chembur, Mumbai | 196 | 32 | 16% |
| Kiwale, Pune | 136 | 32 | 24% |
| Malad West, Mumbai | 192 | 31 | 16% |
| Wakad, Pune | 186 | 29 | 16% |
| Borivali West, Mumbai | 267 | 28 | 10% |
| Mulund West, Mumbai | 197 | 28 | 14% |
| Kothrud, Pune | 190 | 27 | 14% |
| Ghatkopar East, Mumbai | 195 | 26 | 13% |
| Chinchwad, Pune | 95 | 26 | 27% |
| Talegaon Dabhade, Pune | 83 | 25 | 30% |
| Vadavali, Thane | 38 | 24 | 63% |
| Kandivali West, Mumbai | 155 | 23 | 15% |
| Dombivli East, Thane | 119 | 23 | 19% |
| Naupada, Thane | 73 | 22 | 30% |
| Bhandup West, Mumbai | 95 | 22 | 23% |
| Bhiwandi, Thane | 122 | 21 | 17% |
| Goregaon West, Mumbai | 106 | 21 | 20% |
| Kondhwa Budruk, Pune | 82 | 21 | 26% |
| Balewadi, Pune | 145 | 21 | 14% |
| Ulhasnagar, Thane | 58 | 21 | 36% |
| Borivali East, Mumbai | 124 | 21 | 17% |
Lapsed projects by year
| Year the registration lapsed | Lapsed | Extended before lapsing |
|---|---|---|
| 2018 | 97 | 9 (9%) |
| 2019 | 276 | 77 (28%) |
| 2020 | 228 | 118 (52%) |
| 2021 | 480 | 139 (29%) |
| 2022 | 915 | 276 (30%) |
| 2023 | 1,321 | 351 (27%) |
| 2024 | 1,606 | 461 (29%) |
| 2025 | 2,408 | 879 (37%) |
| 2026 (to date) | 1,309 | 609 (47%) |
How these numbers are counted
- Lapsed
- MahaRERA's own Lapsed status: the declared (or extended) completion date has passed with no completion or extension filed. District and locality counts also include deregistered projects.
- Extended before lapsing
- The last completion date on file is later than the date first declared at registration, so the project had been given more time before it lapsed.
- Units sold
- Units the builder reported as sold in the project's latest progress filing. Many older registrations don't list units, so these totals undercount.
- Source
- Public MahaRERA filings only, re-read in batches; most recent filing read 3 Nov 2026. Aggregates only: no individual builder is ranked.
Free to cite
Use these figures in articles, research or reports under CC BY 4.0, with a link back to this page:
AskRera analysis of MahaRERA filings, askrera.com/data/maharera-lapsed-projects/, as of 3 Nov 2026
The project list behind these figures is a free download: MahaRERA registered projects (CSV) .
Questions or a breakdown we don't show? hello@askrera.com. More datasets on the data coverage page.