RERA projects in Solapur district
493 projects are registered with MahaRERA in Solapur. Of the 155 still under construction, 30 have passed the completion date their builder declared to RERA.
125
Ongoing, on schedule
30
Ongoing, past due date
174
Completed
164
Lapsed or deregistered
Most active builders
- M/s Ganesh Ramchandra Apte8
- Dhariwal and Chhoriya Buildcon Pvt Ltd7
- Mohsin Haroon Shaikh6
- Image Space Incorporated5
- Tirupati Construction Promoters & Developers5
- Pandhe Infracons Pvt Ltd4
- Shri R N Goli Developers4
- Shri Samarth Associates3
All projects
Showing 1–100 of 493, newest registrations first.
- Vinayak ResidencyGhodake Developer, MajarewadiPR1320002602377OngoingDec 2028
- Martand EnclaveRajmudra BuildconPR1321012601776OngoingMay 2028
- Aarambha ResidencyAarambha Residency, IsbaviPR1320002601702OngoingJul 2029
- Hexa-Vip PrimeHexaforce Construction LLP, Railway LinesPC1320002601589OngoingDec 2030
- Star AveneuShri Samarth Associates, IsbaviPM1320002601362OngoingDec 2030
- Harisamarth ResidencyShri Samarth Associates, VakhariPM1320002600750OngoingDec 2028
- Shinde ArcadeShinde and Kulkarni Associates, JeurPM1320002600690OngoingDec 2030
- Flora ParkImage Space Incorporated, JulePM1320002600662OngoingMay 2032
- Royal Imperial TowerRoyal Buildcon & AssociatesPR1320002600605OngoingApr 2029
- Royal Residency Building No 4Shubhankar DevelopersPR1320002600339OngoingDec 2027
- Blossom ParkA J BuildconPM1320002502519OngoingMar 2029
- Rita EmpireNeharu NagarPR1320002502449OngoingDec 2030
- Furde Heights-Phase-I,b BuildingSunil Furde Constructions Pvt. Ltd., Rto OfficePR1320002502316OngoingAug 2030
- Vijays the PrestigeGavasane and Khed Builders, Vip RoadP52600081091OngoingAug 2029
- Golden SkylineSavalkar and Sontakale Group, BalePR1321012502057OngoingMar 2029
- Vijayraj VishvaAruna Realtors, MajarewadiPR1320002501716OngoingDec 2032
- Tirupati HarishaTirupati Construction Pramoters and Developers, Gajanan NagarPR1320002501713OngoingDec 2028
- Dhanshree ParkKazi BuildersP52600081055OngoingMar 2028
- Tirupati Puram IITirupati Construction Pramoters and DevelopersPR1320002501514OngoingDec 2030
- Sai Samarth ResidencyNarsigh NagarPR1320002501332OngoingNov 2030
- Rakhi TowerShiva ConstructionPR1320002501254OngoingDec 2028
- Yarawa ResidencyYarawa Buildcon LLP, MajrewadiPR1320002501084OngoingMar 2029
- Kandres Residency A5 BuildingKandre Developer, IsbaviPM1320002501051OngoingDec 2027
- Royal PragatiRoyal Buildcon & Associates, MajrewadiPR1320002500911OngoingMar 2027
- Jijau ResidencyRachana DevelopersPR1320002500779OngoingSept 2029
- Mahanandi HeightsSneharika Vijayshree Developers, ShelagiPR1320002500698OngoingDec 2030
- Shrikhande PrideB. S. L. Developers, IsbaviP52600080909OngoingDec 2027
- Samarth PrasadJJRV Infra Private LimitedPM1320002500526In extensionDec 20304 months late
- Vijayraj SamruddhiOm Realtors, Laxmi Nagar JuleP52600080895OngoingApr 2030
- Mahesh ComplexShri Chaitanya Adhyatmik Trust, Mahesh Sankrutik BhavanPC1320002500410OngoingMar 2030
- Manmeet MandarSolapur Infracons Private LimitedPR1320002500351OngoingMar 2030
- Anantkoti SkyvillaAnantkoti BuildconPM1320002500349OngoingJun 2029
- Deepgiri HeightsP52600080850OngoingDec 2027
- Mithila Golden HeightsAim Properties, DahitaneP52600080754OngoingDec 2027
- Godavari HeightsGayatri Developers, Murarji PethP52600080728OngoingDec 2026
- Raghuraj PrideVasturaj Builders and Developers, IsbaviP52600080721OngoingAug 2027
- Shantais ParadiseShri Samarth Construction, Thakare ChowkP52600080531OngoingDec 2027
- SnehsrusthiGayatri DevelopersP52600080539OngoingDec 2026
- Kimaya Swapanapurti Phase 2Alacrity Constructions Pvt Ltd, Saat RastaP52600080497OngoingDec 2030
- Mahavir HeightsArihant Venkateshwara Infra, KurduwadiP52600080499OngoingDec 2027
- Samruddhi ApartmentAshwa Vishwa Builders Private Limited, BarshiP52600080239LapsedJun 2026
- Skyline SpringsSkyline Builders & DevelopersP52600080202OngoingJan 2027
- Shivyogi ResidencyShelgiP52600080032OngoingDec 2028
- Kimaya SwapanashrusthiKimaya Constructions Pvt Ltd, JuleP52600079814OngoingMar 2030
- Unique ResidencyUnique DevelopersP52600079735OngoingDec 2028
- Gulmohar ResidencyGulmohar ResidencyP52600079681In extensionDec 20283.0 years late
- Madhusudan HeightsSuyash DevelopersP52600079644OngoingDec 2027
- Maner ComplexMadhaP52600079428OngoingDec 2030
- Dwarkadhish EnclaveVaishnavi Construction, Jayjalaram Nagar MajrewadiP52600079368OngoingDec 2026
- Shri Pralhad Smurti ResidencyVijayratna Developers, Pralhad NagarP52600079243OngoingDec 2026
- K-S BougainvilleaKaranje-Surana Constructions Pvt. Ltd., T P IIP52600079195OngoingDec 2029
- KrishnalayamDiddi InfraconsP52600079151OngoingAug 2027
- Royal SynergyShree Jagdamb DevelopersP52600079157OngoingDec 2029
- Royal HeritageMajrewadiP52600079058OngoingMar 2027
- Lotus ApartmentLotus Apartment, Akkalkot MCLP52600078904LapsedMar 2025
- Laxmi ResidencyLaxmikant Infra, Hotagi RoadP52600078797OngoingDec 2027
- Radha Damodar SankulRailway LinesP52600078619OngoingDec 2030
- Bahava ApartmentTauseef Jaweed Shaikh & Jaweed Gulam Shaikh, MajrewadiP52600078480OngoingDec 2027
- Daksh ResidencyBhagyoday Builders, KasbeP52600078465OngoingDec 2027
- Shivtej PlazaEast Mangalwar PethP52600078451OngoingDec 2026
- Paras Business ParkPriyadarshani Corporation, South KasbaP52600077981OngoingDec 2030
- Kaizen EmeraldDhaneshwari NagarP52600077841In extensionDec 202721 months late
- Gawade HeightsP52600077776OngoingDec 2028
- B9 LifestyleBudhwar PethP52600077188OngoingDec 2027
- Aakruti HeritageAakruti DevelopersP52600076988OngoingNov 2027
- Construction of 224 LIG Residential T/S on Land Bearing Survey No 25A/1 Pandharpur Dist SolapurPune Housing and Area Development Board PuneP52600076940OngoingDec 2032
- Vasant ViharV.a. DevelopersP52600076930OngoingMar 2027
- Infinity EnclaveInfinity Reality, Neharu NagarP52600076866OngoingMay 2027
- Somnath HeightsP52600076764OngoingDec 2026
- Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman SansthaAnukarati Homes Private Limited, Solapur NorthP52600076701In extensionDec 202612 months late
- Flora KalpanaImage Space Incorporated, MajarewadiP52600076653OngoingApr 2027
- Pushpakunj ParkManali Realty, PandharpurP52600076604CompletedDec 2028
- Construction of Composite Housing Scheme of 126 T/s EWS and 112 T/s LIGPune Housing and Area Development Board Pune, Soni NagarP52600056169OngoingDec 2032
- Centre CourtMaheshwari Developers, Saat RastaP52600056113OngoingMar 2028
- Green OneP52600055842LapsedMar 2025
- Tirupati PuramTirupati Construction Pramoters and Developers, PandharpurP52600055784OngoingOct 2029
- AkshataKisan Constructions Pvt Ltd, MajarewadiP52600055591CompletedMar 2026
- Patel PlazaEhsan ConstructionP52600055472LapsedDec 2025
- Necklace PrideP52600055508OngoingDec 2027
- Samarth ResidencyNarsinh NagarP52600055390OngoingDec 2027
- Silver ParkV.a. Developers, SangolaP52600055447OngoingDec 2026
- Samruddhi HeightsPragati Associates, PandharpurP52600055310OngoingApr 2028
- Nilayam HeightsP52600055316OngoingDec 2026
- Khushi HeritageKhushi BuildconP52600055164OngoingAug 2026
- Manmeet AbhilashaSolapur Multicons LLP, Budhwar PethP52600055081OngoingMar 2027
- Prajay HeightsJaykant ConstructionP52600055040In extensionMar 202712 months late
- Adinath ApartmentArchit DevelopersP52600054855OngoingDec 2026
- Four SeasonsT6 Realty Pvt Ltd, SoregaonP52600054726CompletedDec 2025
- Sai IconBJR Contructions Private Limited, Murarji PethP52600054657OngoingOct 2027
- Paras ParadiseAnantkoti Developers, Murarji PethP52600054638OngoingMar 2027
- Rushi RichP52600054282OngoingDec 2027
- Tirumala ParadiseJodbhavi PethP52600054305OngoingDec 2026
- Vivek HeightsRailway LineP52600054030OngoingDec 2026
- Kamtam Icon Wing BVishwa DevelopersP52600053917CompletedMar 2027
- Swami Samarth RegencyShri Swami Samarth Developers, Vishal Nagar MajrewadiP52600053627OngoingDec 2026
- Platinum MallM/s Ganesh Ramchandra Apte, Laxmi PethP52600053600OngoingDec 2035
- Royal Residency Building No 2Shubhankar Developers, Mangire MalaP52600053463LapsedMar 2026
- Suyog Shrushti Phase 2Suyog Developers, Ravivar PethP52600053307CompletedMar 2026
- Padmawati RejencyKasbeP52600053139In extensionMar 202712 months late
- Shree Ekdant HeightsPandharpurP52600053183CompletedDec 2025