Delayed projects

MahaRERA delayed projects

Every builder declares a completion date when registering with MahaRERA, and files for an extension when it slips. These figures compare the two across all 50,069 registered projects in Maharashtra, and update as new filings are read.

As of 3 Nov 2026

19,449

Projects under construction

22%

Delayed: completion date pushed back (4,345)

27 mo

Median delay beyond the first declared date

8,992

Registrations lapsed or deregistered

1 in 6

completed projects were delayed first (3,798 of 21,628).

3,347

projects under construction are due to complete in the next 90 days, by their latest filed date.

70

registrations lapsed in the last 90 days. 756 new projects registered in the same period.

Delayed projects by district

Districts with at least 50 projects under construction. Units sold are as filed by builders in their latest progress report.
District Under construction Delayed Median delay Lapsed Units sold
Pune 4,911 25% 24 mo 2,396 43%
Thane 3,121 22% 24 mo 1,187 29%
Mumbai Suburban 2,935 27% 25 mo 1,006 34%
Raigad 1,855 21% 30 mo 1,076 25%
Palghar 1,365 26% 36 mo 420 26%
Nagpur 1,085 14% 30 mo 343 29%
Nashik 1,072 14% 24 mo 478 20%
Aurangabad 424 18% 36 mo 241 12%
Mumbai City 367 25% 38 mo 138 27%
Satara 365 16% 48 mo 237 18%
Ratnagiri 300 17% 33 mo 198 20%
Kolhapur 261 12% 24 mo 136 20%
Sindhudurg 173 20% 38 mo 79 12%
Solapur 155 19% 25 mo 164 10%
Sangli 130 15% 24 mo 183 11%
Ahmednagar 115 7% 40 mo 71 14%
Amravati 90 11% 28 mo 89 7%
Latur 55 16% 12 mo 29 14%

Delayed projects by locality

The 30 localities with the most projects under construction (at least 30 each).

By year of registration

Where each year's registrations stand today. 2017 includes projects already under construction when RERA took effect.
Registered Projects Completed Under construction Lapsed Delayed or lapsed
2017 12,413 74% 8% 18% 46%
2018 3,558 67% 9% 23% 37%
2019 3,876 63% 12% 25% 38%
2020 3,313 54% 15% 31% 45%
2021 4,019 51% 20% 29% 45%
2022 5,451 41% 33% 26% 44%
2023 5,445 23% 57% 19% 35%
2024 4,385 7% 87% 6% 16%
2025 4,285 0% 99% 1% 5%
2026 3,324 0% 100% 0% 2%

How these numbers are counted

Under construction
Registration active, including projects running on an extension. Completed, lapsed and deregistered projects are excluded.
Delayed
The latest proposed completion date on file is later than the date the builder first declared at registration. The delay is the gap between the two.
Lapsed
The declared completion date passed with no completion or extension filed, or MahaRERA deregistered the project. Some lapsed projects are finished on the ground but never filed for completion.
Source
Public MahaRERA filings only, re-read in batches; most recent filing read 3 Nov 2026. Aggregates only: no individual builder is ranked.
Waiting on a delayed flat? → Estimate the interest your builder owes for delayed possession under RERA Section 18 with the delay compensation calculator.

Free to cite

Use these figures in articles, research or reports under CC BY 4.0, with a link back to this page:

AskRera analysis of MahaRERA filings, askrera.com/data/maharera-delayed-projects/, as of 3 Nov 2026