RERA projects in Mundhwa, Pune
89 projects are registered with MahaRERA in Mundhwa, Pune: 60 ongoing, 23 completed, and 6 lapsed, deregistered or in abeyance. 16 are running behind the completion date declared to RERA.
Most active builders here: Speciality Landmarks Private Limited (6), Mantra Zirconia Private Limited (4), Vertical Infra (4), Mantra Skyhomes Private Limited (3), Unique Choice Associates LLP (3).
- Duville AviraPM1260002601985Twin Bungalows Mundhwa LLP · Active · completion Dec 2031
- Anandtara Iris Residences Phase IIIPR1260002600494Anandtara Infrastructure · Active · completion Jun 2029
- Kumar Prism Tower APM1260002501640Kumar Prism Realty LLP · Active · completion Dec 2031
- Indeco Tech ParkPC1260002501497Indeco Developers · Active · completion Mar 2030
- Eleve 1PR1260002501459Vedant Rising Developers · Active · completion Mar 2029
- Newton Home MundhwaPR1261012500924Ravima Venture · Active · completion Dec 2029
- Ace AbundancePR1260002500852Jhamtani Realty Private Limited · Active · completion Mar 2030
- ARV RichvueP52100079608Whitehorse Infra LLP · Active · completion Dec 2029
- Mayfair Residences Phase 1P52100079211Mantra Residencies Erika Private Limited · Active · completion Jun 2029
- Jhamtani ElevateP52100078567Highspot Realty LLP · In extension · completion Apr 2029 · delayed 120d
- Trustfort IconP52100078450Trustfort Realty and Infra LLP · Active · completion Aug 2028
- Mantra Phase 4P52100078311Mantra Skyhomes Private Limited · Active · completion Dec 2032
- Que 914 Phase IIIP52100078292Unique Choice Associates LLP · Active · completion Mar 2028
- CelestiaP52100077933Vinod Suresh Lonkar (Prop. Lonkar Associate) · Active · completion Dec 2027
- Godrej SkylinePM1260002400007Godrej Properties Limited · Active · completion Jul 2029
- Osian Inclusive HousingP52100077263Osian Infratech LLP · Active · completion Dec 2029
- Mantra Phase 3P52100077014Mantra Skyhomes Private Limited · Active · completion Dec 2029
- Mantra Phase 1P52100066482Mantra Skyhomes Private Limited · Active · completion Dec 2029
- Osian Almanova Phase 1P52100056492Osian Infratech LLP · Active · completion Dec 2029
- ZOA Building - 2 Wing AP52100056199Riddhi Siddhi Developers · Active · completion Dec 2028
- Supreme Towers Phase IIP52100056095Eastwood Realty LLP · Active · completion Jun 2029
- Breeza P IIP52100055883A and A Developers · Active · completion Dec 2028
- Mantra Magnus Phase 8P52100055885Speciality Landmarks Private Limited · Active · completion Sept 2029
- Mantra Magnus Phase 7P52100055623Speciality Landmarks Private Limited · Active · completion Sept 2029
- Eastern FrontP52100055529Vishal Anjani Associates LLP · Active · completion Jun 2028
- Clover Business CenterP52100055188Clover Developers Pvt Ltd · In extension · completion Dec 2027 · delayed 366d
- Swami Samarth ResidencyP52100054927Shree Swami Samarth Associates · In extension · completion Dec 2028 · delayed 1096d
- Anandtara Iris Residences Phase IP52100054845Anandtara Infrastructure · In extension · completion Dec 2026 · delayed 184d
- Mantra Magnus Phase 3P52100054483Speciality Landmarks Private Limited · Active · completion Dec 2028
- Mantra Magnus Phase 2P52100054373Speciality Landmarks Private Limited · Active · completion Dec 2028
- Jhamtani BizCoreP52100054261Dusk Realty LLP · In extension · completion Apr 2028 · delayed 121d
- Mantra Magnus Phase 5P52100054231Speciality Landmarks Private Limited · Active · completion Dec 2030
- Supreme Towers Phase IP52100053868Eastwood Realty LLP · Active · completion Jun 2029
- 47 East - C MhadaP52100053775Kumar Properties and Developers LLP · Active · completion Apr 2027
- Atulyam-Inclusive HousingP52100053569Shubh Housing · In extension · completion Apr 2028 · delayed 121d
- Envogue1P52100053239Unique Spaces Landmarks LLP · Active · completion Dec 2028
- 47 East- B (Wing B)P52100052955Kumar Properties and Developers LLP · Active · completion Dec 2028
- S R AkshatamP52100052905S R Buildpro Icon LLP · Active · completion Jul 2027
- Shubh Tristar Wing-AP52100052695Shubh Housing · Active · completion Dec 2027
- Melliza Towers- ResidentialP52100052564Moonlight Housing Schemes LLP · Active · completion Jun 2027
- Que 914 Phase IIP52100051858Unique Choice Associates LLP · Active · completion Jun 2027
- Mantra Mesmer Phase 4P52100049679Mantra Zirconia Private Limited · Active · completion Mar 2028
- Mantra Mirari Phase 3P52100049704Mantra Residences Mundhwa Private Limited · Active · completion Jun 2026
- Platinum Capital Office - Phase IP52100047639A Advani Properties LLP · Active · completion Sept 2026
- Power Heights and Power ResidencesP52100047455Sapra Constructions · Active · completion Dec 2028
- Ganga Avanta A1P52100047366Soham Associates · In extension · completion Dec 2027 · delayed 730d
- 18 EastP52100035065Merlin Projects Limited · In extension · completion Mar 2027 · delayed 182d
- Menlo DeliciaP52100032791Menlo Properties LLP · In extension · completion Oct 2027 · delayed 668d
- Shubh Evan C1 WingP52100026420Kalash Enterprises · In extension · completion Aug 2026 · delayed 609d
- Blossom Park Building BPR1261012601247Unnamed Promoter 240079 · Active · completion Dec 2028
- Raichandani OnePC1260002502623Raichandani Constructions & Developers · Active · completion May 2029
- Media ClassicPR1260002500919Unnamed Promoter 203434 · Active · completion Aug 2028
- Blossom Park Building AP52100080586Unnamed Promoter 194480 · Active · completion Dec 2027
- Mayfair Residences Phase 2P52100079077Mantra Residencies Erika Private Limited · Active · completion Jun 2029
- Indeco SB73P52100077359Indeco Properties · Active · completion Mar 2029
- Shubh Tristar Wing-BP52100055763Shubh Housing · Active · completion Dec 2028
- Mantra Magnus Phase 6P52100054742Speciality Landmarks Private Limited · Active · completion Dec 2030
- Unique Legacy ImperiaP52100053777Unique Buildcon · Completed · completion Mar 2027
- Ace VillasP52100048327Jhamtani Realty Private Limited · In extension · completion Dec 2026 · delayed 365d
- Matoshree PrideP52100048183Unnamed Promoter 106721 · Lapsed · completion Aug 2026 · delayed 365d
- Osian One and Only Phase 2P52100047248Ahura Builders · Completed · completion Dec 2026
- Que 914 Phase IP52100046034Unique Choice Associates LLP · Completed · completion Dec 2026
- Mantra Mirari Phase 2P52100032842Mantra Residences Mundhwa Private Limited · Completed · completion Jun 2026
- Project Abcd Phase 4P52100031240Mantra Zirconia Private Limited · Deregistered · completion Dec 2026
- Horizon HighgrovesP52100030909Yashcon Shelter LLP · Completed · completion Aug 2025
- Mantra Business Centre MundhwaP52100030995Mantra Residences Mundhwa Private Limited · Lapsed · completion Jun 2025
- Osian One and Only Phase IP52100030568Ahura Builders · Completed · completion Jun 2026
- Mantra Mesmer Phase 3P52100030590Mantra Zirconia Private Limited · Active · completion Jun 2026
- AuretaP52100030375M/s Shroff and Choice Constructions LLP · Completed · completion Sept 2025
- Mantra Mesmer Phase 1P52100030387Mantra Zirconia Private Limited · Completed · completion Dec 2026
- Platinum Capital RetailP52100030060A Advani Properties LLP · Lapsed · completion Jan 2026
- Omicron Commerz Koregaon Park NX Phase IP52100029441Bluechip Developments LLP · Completed · completion Dec 2026
- Eves Garden Phase VIP52100028017Sancheti Properties · Lapsed · completion Jun 2024 · delayed 365d
- Savali Saffron Phase IIP52100027901Saptsiddhi Associates · Lapsed · completion Jun 2023
- Nyati Evolve IIIP52100026448Nyati Geeta Associates · Completed · completion Sept 2024
- 47 East - AP52100024598Kumar Properties and Developers LLP · Completed · completion Mar 2027
- Venkatesh Graffiti Elan Phase 1P52100023431Shree Venkatesh Buildcon Pvt Ltd · Completed · completion May 2024
- Nyati Evolve IIP52100022029Nyati Geeta Associates · Completed · completion Sept 2024
- Nyati Evolve IP52100022030Nyati Geeta Associates · Completed · completion Sept 2024
- Vertical Oriana Phase VP52100021565Vertical Infra · In extension · completion Dec 2026 · delayed 1553d
- ShadesP52100017873Suvan Developers · Completed · completion Jul 2023
- Florida River Walk Phase IP52100015819One Earth · Completed · completion Sept 2020
- Savali Saffron Phase - IP52100013111Saptsiddhi Associates · Completed · completion May 2022
- Vertical Oriana Phase IIIP52100005269Vertical Infra · Completed · completion Dec 2021 · delayed 333d
- Gagan UtopiaP52100005074Gagan Buildscapes LLP · Completed · completion Jun 2024 · delayed 1643d
- Eves Garden Phase VP52100004610Sancheti Properties · Completed · completion Jun 2019
- Vertical Oriana Phase IIP52100003699Vertical Infra · Completed · completion Jun 2019
- Vertical Oriana Phase IP52100003700Vertical Infra · Completed · completion Dec 2018
- Belcastel Phase IIP52100002211Sancheti Properties · Completed · completion Dec 2018