Status & progress
Per MahaRERA record as of Oct 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Menlo Properties LLP · Partnership
- Project type
- Residential / Group Housing
- Land area
- 1,520 m² · Permissible built-up (FSI) 4,865 m²
- Total units
- 32 across 1 wing
- Estimated cost
- ₹8.7 Cr
- Application date
- 07 Jan 2022
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 8 of 8 proposed | 32 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- Navin Agarwal · 247
- Structural engineer
- Rajesh Chaudhari
- Project bank
- HDFC BANK
Where it sits
MUNDHWA, Pune — 411036.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Menlo Delicia: common questions
Is Menlo Delicia RERA registered?
Yes. Menlo Delicia is registered with MahaRERA under registration number P52100032791, granted on 29 January 2022. As of October 2026, the registration is active under a MahaRERA extension.
What is the possession date of Menlo Delicia?
The developer has declared completion by October 2027 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 668 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Menlo Delicia?
Menlo Delicia is developed by Menlo Properties LLP, the promoter named in its MahaRERA registration.
Where is Menlo Delicia located?
Menlo Delicia is in Mundhwa, Pune (PIN 411036), Maharashtra, as declared in its RERA registration.
How many units does Menlo Delicia have, and how many are sold?
Menlo Delicia has 32 units on its RERA registration. 10 were reported sold as of October 2026, leaving 22 unsold.
How much construction of Menlo Delicia is complete?
By the developer's own quarterly filing, 100% of the work is done, measured against the project's cost estimate.
Is there any litigation against Menlo Delicia?
No litigation is declared on Menlo Delicia's MahaRERA record as of October 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Mundhwa
- Duville Avira · Pune
- Anandtara Iris Residences Phase III · Pune
- Kumar Prism Tower A · Pune
- Indeco Tech Park · Pune
- Eleve 1 · Pune
- Newton Home Mundhwa · Pune
- Ace Abundance · Pune
- ARV Richvue · Pune