ActivePM1260002501640Registered Dec 2025No active red flags

Kumar Prism Tower A

A mixed project by Kumar Prism Realty LLP in Mundhwa, Pune.

Data as of May 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of May 2026.

Construction
0%
cost-weighted
Declared completion
Dec 2031
no delay on record
Units sold
0 / 82
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Kumar Prism Realty LLP · Partnership
Project type
Mixed
Land area
14,203 m² · Permissible built-up (FSI) 14,595 m²
Total units
82 across 1 wing
Estimated cost
₹137 Cr
Parking
333 four-wheeler · 223 two-wheeler
Application date
28 Oct 2025
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA20 of 34 proposed82
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Voussoirs · CA/92/14618
Structural engineer
Project bank
HDFC BANK
Location

Where it sits

Mundhwa, Pune — 411036.

Locality
Mundhwa
District
Pune
Authority
Pune mahanagar palika
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Kumar Prism Tower A: common questions

Is Kumar Prism Tower A RERA registered?

Yes. Kumar Prism Tower A is registered with MahaRERA under registration number PM1260002501640, granted on 2 December 2025. As of May 2026, the registration is active.

What is the possession date of Kumar Prism Tower A?

The developer has declared completion by December 2031 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Kumar Prism Tower A?

Kumar Prism Tower A is developed by Kumar Prism Realty LLP, the promoter named in its MahaRERA registration.

Where is Kumar Prism Tower A located?

Kumar Prism Tower A is in Mundhwa, Pune (PIN 411036), Maharashtra, as declared in its RERA registration.

How many units does Kumar Prism Tower A have, and how many are sold?

Kumar Prism Tower A has 82 units on its RERA registration. 0 were reported sold as of May 2026, leaving 82 unsold.

How much construction of Kumar Prism Tower A is complete?

By the developer's own quarterly filing, 0% of the work is done, measured against the project's cost estimate.

Is there any litigation against Kumar Prism Tower A?

No litigation is declared on Kumar Prism Tower A's MahaRERA record as of May 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Mundhwa

All RERA projects in Mundhwa →