In ExtensionP51700028265Registered Feb 2021Delayed 1280dExtension1 red flag

Enviro Affinity

A residential / group housing project by Aristone Developers in GAURAV CITY, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
26%
cost-weighted
Declared completion
Dec 2028
delayed 1280d
Units sold
0 / 161
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Aristone Developers · Partnership
Project type
Residential / Group Housing
Land area
475 m² · Permissible built-up (FSI) 7,292 m²
Total units
161 across 1 wing
Estimated cost
₹33 Cr
Land ownership
Promoter is the landowner
Application date
19 Jan 2021
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA24 of 24 proposed161
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
ANISH & ASSOCIATES · k/386/Is
Structural engineer
SUBHASH SINGH · S/755/SS-I
Project bank
ICICI BANK LIMITED
Location

Where it sits

GAURAV CITY, Thane — 401107.

Locality
GAURAV CITY
District
Thane
Authority
mira bhayander municipal corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

Enviro Affinity: common questions

Is Enviro Affinity RERA registered?

Yes. Enviro Affinity is registered with MahaRERA under registration number P51700028265, granted on 18 February 2021. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Enviro Affinity?

The developer has declared completion by December 2028 in its MahaRERA filing, revised from the original June 2025. The record shows the project running 1280 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Enviro Affinity?

Enviro Affinity is developed by Aristone Developers, the promoter named in its MahaRERA registration.

Where is Enviro Affinity located?

Enviro Affinity is in Gaurav City, Thane (PIN 401107), Maharashtra, as declared in its RERA registration.

How many units does Enviro Affinity have, and how many are sold?

Enviro Affinity has 161 units on its RERA registration. 0 were reported sold as of July 2026, leaving 161 unsold.

How much construction of Enviro Affinity is complete?

By the developer's own quarterly filing, 26% of the work is done, measured against the project's cost estimate.

Is there any litigation against Enviro Affinity?

No litigation is declared on Enviro Affinity's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

RERA projects nearby