Mayfair Palmeira
A others project by Mayfair Maru Developers in MIRA ROAD EST, Thane.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Mayfair Maru Developers · Partnership
- Project type
- Others
- Land area
- 8,423 m² · Permissible built-up (FSI) 47,576 m²
- Total units
- 480 across 3 wings
- Estimated cost
- ₹307 Cr
- Parking
- 644 four-wheeler · 92 two-wheeler
- Held outside open sale
- 38 reserved
- Application date
- 26 Jul 2017
3 wings
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 6 of 6 proposed | 24 |
| NA | 38 of 38 proposed | 228 |
| NA | 38 of 38 proposed | 228 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- JAI MISTRY · CA/2001/28168
- Structural engineer
- S S PATANE ASSOCIATES · STR/P/170
- Project bank
- ICICI BANK LIMITED
Where it sits
MIRA ROAD EST, Thane — 401107.
1 flag on this project
What they are and why they matter — in the full report.
Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.
Unlock full report — ₹99Why these flags matter
Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.
Unlock full report — ₹99Complaints, litigation & charges
Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.
Unlock full report — ₹99Mayfair Palmeira: common questions
Is Mayfair Palmeira RERA registered?
Yes. Mayfair Palmeira is registered with MahaRERA under registration number P51700002231, granted on 31 July 2017. As of July 2026, the registration is active under a MahaRERA extension.
What is the possession date of Mayfair Palmeira?
The developer has declared completion by December 2031 in its MahaRERA filing, revised from the original December 2028. The record shows the project running 1096 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Mayfair Palmeira?
Mayfair Palmeira is developed by Mayfair Maru Developers, the promoter named in its MahaRERA registration.
Where is Mayfair Palmeira located?
Mayfair Palmeira is in Mira Road Est, Thane (PIN 401107), Maharashtra, as declared in its RERA registration.
How many units does Mayfair Palmeira have, and how many are sold?
Mayfair Palmeira has 480 units on its RERA registration. 41 were reported sold as of July 2026, leaving 439 unsold.
How much construction of Mayfair Palmeira is complete?
By the developer's own quarterly filing, 10% of the work is done, measured against the project's cost estimate.
Is there any litigation against Mayfair Palmeira?
7 litigation cases are declared on Mayfair Palmeira's MahaRERA record. The full report lists each case with its court and status.
RERA projects nearby
- Jyoti Breeze · Thane
- Shree Haven · Thane
- The Address Building No.5 · Thane
- Tiara Hills Phase I BLDG No 3, 5 and 2 · Thane
- Krishna Prestige · Thane
- Gaurav Aster · Thane
- Sai Enclave · Thane
- Umiya Oasis · Thane