In ExtensionP51700010406Registered Aug 2017Delayed 365dExtension1 red flag

Tiara Hills Phase I BLDG No 3, 5 and 2

A residential / group housing project by PNK Space Development Pvt Ltd in MIRA ROAD EAST, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
76%
cost-weighted
Declared completion
Dec 2026
delayed 365d
Units sold
619 / 1028
60% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
PNK Space Development Pvt Ltd · Company
Project type
Residential / Group Housing
Land area
18,946 m² · Permissible built-up (FSI) 56,390 m²
Total units
1028 across 3 wings
Estimated cost
₹160.6 Cr
Land ownership
Promoter is the landowner
Parking
442 four-wheeler · 51 two-wheeler
Application date
31 Jul 2017
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA26 of 26 proposed290
NA26 of 26 proposed336
NA26 of 26 proposed402
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
NIRMEEK ASSOCIATES · CA/2008/42274
Structural engineer
FINITE CONSULTANTS
Project bank
KOTAK MAHINDRA BANK LIMITED
Location

Where it sits

MIRA ROAD EAST, Thane — 401107.

Locality
MIRA ROAD EAST
District
Thane
Authority
MIRA BHAINDAR MUNICIPAL CORPORATION
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Tiara Hills Phase I BLDG No 3, 5 and 2: common questions

Is Tiara Hills Phase I BLDG No 3, 5 and 2 RERA registered?

Yes. Tiara Hills Phase I BLDG No 3, 5 and 2 is registered with MahaRERA under registration number P51700010406, granted on 24 August 2017. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Tiara Hills Phase I BLDG No 3, 5 and 2?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Tiara Hills Phase I BLDG No 3, 5 and 2?

Tiara Hills Phase I BLDG No 3, 5 and 2 is developed by PNK Space Development Pvt Ltd, the promoter named in its MahaRERA registration.

Where is Tiara Hills Phase I BLDG No 3, 5 and 2 located?

Tiara Hills Phase I BLDG No 3, 5 and 2 is in Mira Road East, Thane (PIN 401107), Maharashtra, as declared in its RERA registration.

How many units does Tiara Hills Phase I BLDG No 3, 5 and 2 have, and how many are sold?

Tiara Hills Phase I BLDG No 3, 5 and 2 has 1028 units on its RERA registration. 661 were reported sold as of July 2026, leaving 367 unsold.

How much construction of Tiara Hills Phase I BLDG No 3, 5 and 2 is complete?

By the developer's own quarterly filing, 76% of the work is done, measured against the project's cost estimate.

Is there any litigation against Tiara Hills Phase I BLDG No 3, 5 and 2?

5 litigation cases are declared on Tiara Hills Phase I BLDG No 3, 5 and 2's MahaRERA record. The full report lists each case with its court and status.

More RERA projects in Mira Road East

All RERA projects in Mira Road East →