In ExtensionP51700010579Registered Aug 2017Delayed 2100dExtension2 red flags

Goldcrest Residency - Phase 2

A residential / group housing project by Savita Homemakers LLP in GHANSOLI, Thane.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
88%
cost-weighted
Declared completion
Mar 2027
delayed 2100d
Units sold
310 / 316
98% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Savita Homemakers LLP · Partnership
Project type
Residential / Group Housing
Land area
7,025 m² · Permissible built-up (FSI) 11,138 m²
Total units
316 across 3 wings
Estimated cost
₹134.8 Cr
Application date
28 Jul 2017
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA30 of 30 proposed91
NA30 of 30 proposed134
NA30 of 30 proposed91
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Soyuz Talib · CA/94/17095
Structural engineer
· 840018856
Project bank
INDUSIND BANK
Location

Where it sits

GHANSOLI, Thane — 400701.

Locality
GHANSOLI
District
Thane
Authority
Navi Mumbai Municipal Corporation
Red flags

2 flags on this project

What they are and why they matter — in the full report.

Unlock the 2 red flags on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Goldcrest Residency - Phase 2: common questions

Is Goldcrest Residency - Phase 2 RERA registered?

Yes. Goldcrest Residency - Phase 2 is registered with MahaRERA under registration number P51700010579, granted on 31 August 2017. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Goldcrest Residency - Phase 2?

The developer has declared completion by March 2027 in its MahaRERA filing, revised from the original June 2021. The record shows the project running 2100 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Goldcrest Residency - Phase 2?

Goldcrest Residency - Phase 2 is developed by Savita Homemakers LLP, the promoter named in its MahaRERA registration.

Where is Goldcrest Residency - Phase 2 located?

Goldcrest Residency - Phase 2 is in Ghansoli, Thane (PIN 400701), Maharashtra, as declared in its RERA registration.

How many units does Goldcrest Residency - Phase 2 have, and how many are sold?

Goldcrest Residency - Phase 2 has 316 units on its RERA registration. 316 were reported sold as of September 2026, leaving 0 unsold.

How much construction of Goldcrest Residency - Phase 2 is complete?

By the developer's own quarterly filing, 88% of the work is done, measured against the project's cost estimate.

Is there any litigation against Goldcrest Residency - Phase 2?

2 litigation cases are declared on Goldcrest Residency - Phase 2's MahaRERA record. The full report lists each case with its court and status.