In ExtensionP52100024921Registered Mar 2020Delayed 1462dExtension1 red flag

Up-Life-Phase-5-Ivory

A residential / group housing project by Avior Shelters LLP in -, Pune.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
31%
cost-weighted
Declared completion
Dec 2029
delayed 1462d
Units sold
5 / 44
11% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Avior Shelters LLP · Partnership
Project type
Residential / Group Housing
Land area
2,067 m² · Permissible built-up (FSI) 4,199 m²
Total units
44 across 1 wing
Estimated cost
₹12.5 Cr
Land ownership
Promoter is the landowner
Held outside open sale
24 landowner/investor share
Application date
29 Feb 2020
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA4 of 4 proposed44
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
· CA/2005/37015
Structural engineer
· REG/PMC/STE/0580/25
Project bank
HDFC BANK
Location

Where it sits

-, Pune — 412108.

Locality
-
District
Pune
Authority
PUNE METROPOLITAN REGION DEVELOPMENT AUTHORITY, PUNE
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Up-Life-Phase-5-Ivory: common questions

Is Up-Life-Phase-5-Ivory RERA registered?

Yes. Up-Life-Phase-5-Ivory is registered with MahaRERA under registration number P52100024921, granted on 12 March 2020. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Up-Life-Phase-5-Ivory?

The developer has declared completion by December 2029 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 1462 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Up-Life-Phase-5-Ivory?

Up-Life-Phase-5-Ivory is developed by Avior Shelters LLP, the promoter named in its MahaRERA registration.

Where is Up-Life-Phase-5-Ivory located?

Up-Life-Phase-5-Ivory is in Pune (PIN 412108), Maharashtra, as declared in its RERA registration.

How many units does Up-Life-Phase-5-Ivory have, and how many are sold?

Up-Life-Phase-5-Ivory has 44 units on its RERA registration. 6 were reported sold as of September 2026, leaving 38 unsold.

How much construction of Up-Life-Phase-5-Ivory is complete?

By the developer's own quarterly filing, 31% of the work is done, measured against the project's cost estimate.

Is there any litigation against Up-Life-Phase-5-Ivory?

No litigation is declared on Up-Life-Phase-5-Ivory's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.