In ExtensionP51800011437Registered Aug 2017Delayed 1309dExtension2 red flags

Sheetal Tapovan

A residential / group housing project by DGS Township Pvt Ltd in GOREGAON EAST, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
97%
cost-weighted
Declared completion
Dec 2026
delayed 1309d
Units sold
0 / 273
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
DGS Township Pvt Ltd · Company
Project type
Residential / Group Housing
Land area
4,653 m² · Permissible built-up (FSI) 23,111 m²
Total units
273 across 1 wing
Estimated cost
₹192.2 Cr
Land ownership
Promoter is the landowner
Application date
31 Jul 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA28 of 28 proposed273
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
RASIK HINGOO
Structural engineer
HIREN TANNA
Project bank
STATE BANK OF INDIA
Location

Where it sits

GOREGAON EAST, Mumbai Suburban — 400097.

Locality
GOREGAON EAST
District
Mumbai Suburban
Authority
MUNICIPAL CORPORATION OF GREATER MUMBAI
Red flags

2 flags on this project

What they are and why they matter — in the full report.

Unlock the 2 red flags on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Sheetal Tapovan: common questions

Is Sheetal Tapovan RERA registered?

Yes. Sheetal Tapovan is registered with MahaRERA under registration number P51800011437, granted on 31 August 2017. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Sheetal Tapovan?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original June 2023. The record shows the project running 1309 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Sheetal Tapovan?

Sheetal Tapovan is developed by DGS Township Pvt Ltd, the promoter named in its MahaRERA registration.

Where is Sheetal Tapovan located?

Sheetal Tapovan is in Goregaon East, Mumbai (PIN 400097), Maharashtra, as declared in its RERA registration.

How many units does Sheetal Tapovan have, and how many are sold?

Sheetal Tapovan has 273 units on its RERA registration. 264 were reported sold as of September 2026, leaving 9 unsold.

How much construction of Sheetal Tapovan is complete?

By the developer's own quarterly filing, 97% of the work is done, measured against the project's cost estimate.

Is there any litigation against Sheetal Tapovan?

No litigation is declared on Sheetal Tapovan's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Goregaon East