ActiveP51800079181Registered Feb 20251 red flag

S-City-R2

A others project by Alchemi Developers Private Limited in Malad (E), Goregaon (E), Mumbai Suburban.

Data as of Oct 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Oct 2026.

Construction
6%
cost-weighted
Declared completion
Dec 2030
no delay on record
Units sold
0 / 86
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Alchemi Developers Private Limited · Company
Project type
Others
Land area
2,977 m² · Permissible built-up (FSI) 55,046 m²
Total units
86 across 1 wing
Estimated cost
₹293.9 Cr
Application date
23 Jan 2025
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA38 of 38 proposed86
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
ANIKET BANDRE ( A B ASSOCIATES)
Structural engineer
J W CONSULTANTS LLP
Project bank
ICICI BANK LIMITED
Location

Where it sits

Malad (E), Goregaon (E), Mumbai Suburban — 400063.

Locality
Malad (E), Goregaon (E)
District
Mumbai Suburban
Authority
Slum Rehabilitation Authority
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

S-City-R2: common questions

Is S-City-R2 RERA registered?

Yes. S-City-R2 is registered with MahaRERA under registration number P51800079181, granted on 14 February 2025. As of October 2026, the registration is active.

What is the possession date of S-City-R2?

The developer has declared completion by December 2030 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of S-City-R2?

S-City-R2 is developed by Alchemi Developers Private Limited, the promoter named in its MahaRERA registration.

Where is S-City-R2 located?

S-City-R2 is in Goregaon East, Mumbai (PIN 400063), Maharashtra, as declared in its RERA registration.

How many units does S-City-R2 have, and how many are sold?

S-City-R2 has 86 units on its RERA registration. 1 were reported sold as of October 2026, leaving 85 unsold.

How much construction of S-City-R2 is complete?

By the developer's own quarterly filing, 6% of the work is done, measured against the project's cost estimate.

Is there any litigation against S-City-R2?

11 litigation cases are declared on S-City-R2's MahaRERA record. The full report lists each case with its court and status.

More RERA projects in Goregaon East

All RERA projects in Goregaon East →

Other projects by Alchemi Developers Private Limited

All projects by Alchemi Developers Private Limited →