In ExtensionP51800052788Registered Sept 2023Delayed 365dExtension1 red flag

Ruparel Crest

A others project by Bharat Mahan Developers & Builders in Kurla East, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
58%
cost-weighted
Declared completion
Dec 2026
delayed 365d
Units sold
230 / 277
83% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Bharat Mahan Developers & Builders · Partnership
Project type
Others
Land area
3,302 m² · Permissible built-up (FSI) 16,501 m²
Total units
277 across 3 wings
Estimated cost
₹113.1 Cr
Parking
152 four-wheeler · 0 two-wheeler
Application date
09 Aug 2023
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA19 of 19 proposed112
NA18 of 18 proposed113
NA18 of 18 proposed52
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Rahul Kamathi
Structural engineer
JW Consultants
Project bank
ICICI BANK LIMITED
Location

Where it sits

Kurla East, Mumbai Suburban — 400024.

Locality
Kurla East
District
Mumbai Suburban
Authority
Slum Rehabilitation Authority
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Ruparel Crest: common questions

Is Ruparel Crest RERA registered?

Yes. Ruparel Crest is registered with MahaRERA under registration number P51800052788, granted on 25 September 2023. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Ruparel Crest?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Ruparel Crest?

Ruparel Crest is developed by Bharat Mahan Developers & Builders, the promoter named in its MahaRERA registration.

Where is Ruparel Crest located?

Ruparel Crest is in Kurla East, Mumbai (PIN 400024), Maharashtra, as declared in its RERA registration.

How many units does Ruparel Crest have, and how many are sold?

Ruparel Crest has 277 units on its RERA registration. 230 were reported sold as of September 2026, leaving 47 unsold.

How much construction of Ruparel Crest is complete?

By the developer's own quarterly filing, 58% of the work is done, measured against the project's cost estimate.

Is there any litigation against Ruparel Crest?

No litigation is declared on Ruparel Crest's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.