ActiveP51700030509Registered Aug 20211 red flag

Raheja Solaris-1

A residential / group housing project by Raheja Universal (Pvt.) Ltd. in TTC Industrial Area, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
76%
cost-weighted
Declared completion
Dec 2026
no delay on record
Units sold
440 / 441
100% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Raheja Universal (Pvt.) Ltd. · Company
Project type
Residential / Group Housing
Land area
2,23,309 m² · Permissible built-up (FSI) 20,897 m²
Total units
441 across 2 wings
Estimated cost
₹272.2 Cr
Application date
03 Aug 2021
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA30 of 30 proposed196
NA31 of 31 proposed245
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Ar. Kamal Khemani · CA/99/24971
Structural engineer
Mahesh Lalla · SUP/Grade-1:840006956
Project bank
HDFC BANK
Location

Where it sits

TTC Industrial Area, Thane — 400705.

Locality
TTC Industrial Area
District
Thane
Authority
Maharashtra Industrial Development Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Raheja Solaris-1: common questions

Is Raheja Solaris-1 RERA registered?

Yes. Raheja Solaris-1 is registered with MahaRERA under registration number P51700030509, granted on 30 August 2021. As of July 2026, the registration is active.

What is the possession date of Raheja Solaris-1?

The developer has declared completion by December 2026 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Raheja Solaris-1?

Raheja Solaris-1 is developed by Raheja Universal (Pvt.) Ltd., the promoter named in its MahaRERA registration.

Where is Raheja Solaris-1 located?

Raheja Solaris-1 is in TTC Industrial Area, Thane (PIN 400705), Maharashtra, as declared in its RERA registration.

How many units does Raheja Solaris-1 have, and how many are sold?

Raheja Solaris-1 has 441 units on its RERA registration. 440 were reported sold as of July 2026, leaving 1 unsold.

How much construction of Raheja Solaris-1 is complete?

By the developer's own quarterly filing, 76% of the work is done, measured against the project's cost estimate.

Is there any litigation against Raheja Solaris-1?

No litigation is declared on Raheja Solaris-1's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.