Presidential Park Phase 2
A plotted project by Oneness Realtors in Mawal, Pune.
Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Sept 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Oneness Realtors · Partnership
- Project type
- Plotted
- Land area
- 22,900 m²
- Total units
- 39
- Estimated cost
- ₹0.8 Cr
- Application date
- 30 Dec 2023
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- Atit Admulwar Planners (OPC) PVT. LTD. · CA/2008/41887
- Structural engineer
- Rohinee Engineers · PCMC/LE/0651/2017
- Project bank
- ICICI BANK LIMITED
Where it sits
Mawal, Pune — 412106.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Presidential Park Phase 2: common questions
Is Presidential Park Phase 2 RERA registered?
Yes. Presidential Park Phase 2 is registered with MahaRERA under registration number P52100054843, granted on 15 February 2024. As of September 2026, the registration is active under a MahaRERA extension.
What is the possession date of Presidential Park Phase 2?
The developer has declared completion by October 2026 in its MahaRERA filing, revised from the original December 2024. The record shows the project running 669 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Presidential Park Phase 2?
Presidential Park Phase 2 is developed by Oneness Realtors, the promoter named in its MahaRERA registration.
Where is Presidential Park Phase 2 located?
Presidential Park Phase 2 is in Mawal, Pune (PIN 412106), Maharashtra, as declared in its RERA registration.
How many units does Presidential Park Phase 2 have, and how many are sold?
Presidential Park Phase 2 has 39 units on its RERA registration. 27 were reported sold as of September 2026, leaving 12 unsold.
How much construction of Presidential Park Phase 2 is complete?
By the developer's own quarterly filing, 100% of the work is done, measured against the project's cost estimate.
Is there any litigation against Presidential Park Phase 2?
No litigation is declared on Presidential Park Phase 2's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Mawal
- VSG Suraksha Enclave · Pune
- Rakshak Vatika A B C wings · Pune
- Spot One · Pune
- Bhakti Aangan · Pune
- Samarth Heights · Pune
- Residential Building on CTS No 107/1P -GIRIVAR RESIDENCY · Pune
- Surya Heights · Pune
- Sahyadri Complex · Pune