In ExtensionP52100020919Registered May 2019Delayed 2590dExtension1 red flag

Bhakti Aangan

A residential / group housing project by Nirmiti Developers in VADGAON MAVAL, Pune.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
52%
cost-weighted
Declared completion
Dec 2028
delayed 2590d
Units sold
0 / 32
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Nirmiti Developers · Partnership
Project type
Residential / Group Housing
Land area
948 m² · Permissible built-up (FSI) 1,086 m²
Total units
32 across 2 wings
Estimated cost
₹2.6 Cr
Land ownership
Promoter is the landowner
Parking
10 four-wheeler · 30 two-wheeler
Held outside open sale
12 landowner/investor share
Application date
15 May 2019
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA5 of 5 proposed16
NA5 of 5 proposed16
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
M J ASSOCIATES · PCMC/0607/2018
Structural engineer
RAVINDRA A KARNAVAT AND ASSOCIATES
Project bank
GS Mahanagar Co-operative Bank Limited, Mumbai
Location

Where it sits

VADGAON MAVAL, Pune — 412106.

Locality
VADGAON MAVAL
District
Pune
Authority
Pune Metropolitan Region Development Authority
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

Bhakti Aangan: common questions

Is Bhakti Aangan RERA registered?

Yes. Bhakti Aangan is registered with MahaRERA under registration number P52100020919, granted on 23 May 2019. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Bhakti Aangan?

The developer has declared completion by December 2028 in its MahaRERA filing, revised from the original November 2021. The record shows the project running 2590 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Bhakti Aangan?

Bhakti Aangan is developed by Nirmiti Developers, the promoter named in its MahaRERA registration.

Where is Bhakti Aangan located?

Bhakti Aangan is in Vadgaon Maval, Pune (PIN 412106), Maharashtra, as declared in its RERA registration.

How many units does Bhakti Aangan have, and how many are sold?

Bhakti Aangan has 32 units on its RERA registration. 0 were reported sold as of September 2026, leaving 32 unsold.

How much construction of Bhakti Aangan is complete?

By the developer's own quarterly filing, 52% of the work is done, measured against the project's cost estimate.

Is there any litigation against Bhakti Aangan?

No litigation is declared on Bhakti Aangan's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Vadgaon Maval

All RERA projects in Vadgaon Maval →