In ExtensionP51700026067Registered Aug 2020Delayed 730dExtension1 red flag

Mali Pinnacle

A residential / group housing project by Mali Infra in HAJIMALANG ROAD, Thane.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
81%
cost-weighted
Declared completion
Jan 2027
delayed 730d
Units sold
80 / 113
71% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Mali Infra · Partnership
Project type
Residential / Group Housing
Land area
2,150 m² · Permissible built-up (FSI) 2,324 m²
Total units
113 across 1 wing
Estimated cost
₹17.2 Cr
Land ownership
Promoter is the landowner
Held outside open sale
32 landowner/investor share
Application date
01 Aug 2020
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA30 of 30 proposed113
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
AR MADAN GADGIL · CA/98/23874
Structural engineer
ER ATUL KURTADKAR · STATE/R/2025/APL/16827
Project bank
HDFC BANK
Location

Where it sits

HAJIMALANG ROAD, Thane — 421306.

Locality
HAJIMALANG ROAD
District
Thane
Authority
Kalyan Dombivali Municipal Corporation, Kalyan
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Mali Pinnacle: common questions

Is Mali Pinnacle RERA registered?

Yes. Mali Pinnacle is registered with MahaRERA under registration number P51700026067, granted on 15 August 2020. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Mali Pinnacle?

The developer has declared completion by January 2027 in its MahaRERA filing, revised from the original January 2025. The record shows the project running 730 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Mali Pinnacle?

Mali Pinnacle is developed by Mali Infra, the promoter named in its MahaRERA registration.

Where is Mali Pinnacle located?

Mali Pinnacle is in Hajimalang Road, Thane (PIN 421306), Maharashtra, as declared in its RERA registration.

How many units does Mali Pinnacle have, and how many are sold?

Mali Pinnacle has 113 units on its RERA registration. 79 were reported sold as of September 2026, leaving 34 unsold.

How much construction of Mali Pinnacle is complete?

By the developer's own quarterly filing, 81% of the work is done, measured against the project's cost estimate.

Is there any litigation against Mali Pinnacle?

No litigation is declared on Mali Pinnacle's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.

RERA projects nearby

Other projects by Mali Infra

All projects by Mali Infra →