RERA projects in Mohammadwadi, Pune
50 projects are registered with MahaRERA in Mohammadwadi, Pune: 22 ongoing, 16 completed, and 12 lapsed, deregistered or in abeyance. 19 are running behind the completion date declared to RERA.
Most active builders here: Lodha Developers Limited (3), Hasthshilp Reality (3), Nyati Builders Private Limited (3), M/s Namo Developers (3), Cavalcade Properties Private Limited (3).
- StellarisPM1260002600384Unitary Cityspace Private Limited · Active · completion Mar 2030
- Bhoomi ArcadiaPR1260002502900Bhoomi Buildcon · Active · completion Dec 2029
- Aura AiwaP52100080590Skyscapes Homes LLP · Active · completion Dec 2028
- Aviro SquareP52100079657Krishna Vision · Active · completion Dec 2027
- Ganga Imperia BLDG AP52100079248Ganraj Homes LLP · Active · completion Mar 2030
- Rezo Phase 1P52100078220Triaa Square LLP · Active · completion Dec 2030
- Somnath VastuP52100055733Sairaj Constructions · Active · completion Dec 2027
- Moreshwar EnclaveP52100055219Moreshwar Developers · In extension · completion Dec 2026 · delayed 579d
- ConstellaP52100054947Peridot Lifespaces LLP · Active · completion Dec 2028
- The HyphenP52100054125Dynasty Agr Constro LLP · Active · completion Dec 2029
- Lodha Bella Vita SignetP52100047378Lodha Developers Limited · Active · completion Dec 2026
- Shankeshwar Business Hub Phase IIP52100046856Arunita Landmarks · In extension · completion Dec 2027 · delayed 730d
- Shankeshwar Business Hub Phase 1P52100046539Arunita Developers · In extension · completion Dec 2027 · delayed 730d
- Lodha Pune NIBM Project- Tower 7,8 and 9P52100046081Lodha Developers Limited · Active · completion Dec 2027
- Shivam HeightsP52100028393M/s Space Realtor · In extension · completion Mar 2027 · delayed 1187d
- Arnav Sokande Patil PlazaP52100027150Sokande Patil Prom & Developers · In extension · completion Nov 2026 · delayed 1251d
- Sky GardensP52100016753Apk Landmarks LLP · In extension · completion Aug 2027 · delayed 974d
- Vertical Alcinia Phase IIIP52100011957Hasthshilp Reality · In extension · completion Jan 2027 · delayed 2132d
- TensidePR1260002502245Unnamed Promoter 209804 · Active · completion Nov 2027
- Ganga Imperia CommercialPC1260002501197Ganraj Homes LLP · Active · completion Dec 2029
- Sahil VatikaP52100079705Unnamed Promoter 95382 · Active · completion Dec 2028
- Lantana Court A BuildingP52100079600Landmark Ventures · Active · completion Jul 2027
- Golden PlazaP52100049432Ganraj Properties · Lapsed · completion Dec 2025 · delayed 332d
- Nyati Exuberance IIP52100048720Nyati Builders Private Limited · Lapsed · completion Mar 2025
- AviroP52100045561Krishna Vision · Lapsed · completion Jun 2026 · delayed 365d
- Lodha Pune NIBM Project-Tower 6P52100034751Lodha Developers Limited · Completed · completion Dec 2026
- Nyati Exuberance IIIP52100034932Nyati Builders Private Limited · Completed · completion Jun 2025 · delayed 365d
- Fortune PrimaP52100034021Unnamed Promoter 95254 · Completed · completion Sept 2026
- Ganraj SkydaleP52100028527Ganraj Associates · Lapsed · completion Apr 2026
- Eden GardenP52100027739Unnamed Promoter 116339 · Lapsed · completion Jun 2024
- Nyati Exuberance IP52100027031Nyati Builders Private Limited · Lapsed · completion Sept 2025 · delayed 365d
- Archana Paradise Wing AP52100026701Kanifnath Reality · Completed · completion Jun 2024
- West Woods 1P52100025785The Skyline Developers · Completed · completion Mar 2025 · delayed 630d
- Madhuvan 5 76CP52100025506Magarpatta City Development Co. Pvt. Ltd. · Lapsed · completion Dec 2024
- Madhuvan 6 76DP52100025448Magarpatta City Development Company Pvt. Ltd. · Lapsed · completion Dec 2024
- Madhuvan 4 76BP52100025447Magarpatta City Development Co. Pvt. Ltd. · Lapsed · completion Dec 2024
- Forest ViewP52100024124Seven Seas Developers · Lapsed · completion Dec 2024 · delayed 731d
- Memories 90 -Phase IIIP52100023691M/s Namo Developers · Completed · completion Dec 2025
- Voyage to the stars - CommercialP52100020446Acropolis Purple Developers · Completed · completion Mar 2025 · delayed 732d
- Memories 90 - Phase IIP52100020409M/s Namo Developers · Completed · completion Dec 2024
- Vistas CentrepointP52100016359Cavalcade Properties Private Limited · Completed · completion Dec 2021
- T12 Named Magna Being Phase 2 of the Project Comprising Buildings T12 and T13P52100015996Cavalcade Properties Private Limited · Completed · completion Dec 2019
- Ganga Kingston Building GP52100015357Vedant Construction · Completed · completion Dec 2021
- Memories 90 - CommercialP52100013482M/s Namo Developers · Completed · completion Dec 2022
- Vertical Alcinia Phase IIP52100012117Hasthshilp Reality · Completed · completion Oct 2022 · delayed 659d
- Vertical Alcinia Phase IP52100007827Hasthshilp Reality · Completed · completion Dec 2020 · delayed 548d
- Cleveland ParkP52100003050Vardaan Lifestyle Limited · Lapsed · completion Sept 2026 · delayed 1370d
- Gagan ElaP52100002439Gagan Landmarks LLP · Completed · completion Jun 2025 · delayed 1642d
- Marvel Isola J BuildingP52100001843Marvel Landmarks Pvt Ltd · Lapsed · completion Jun 2026 · delayed 1826d
- T13 - Phase of the Project Comprising Building T12 and T13P52100000707Cavalcade Properties Private Limited · Completed · completion Dec 2018