In ExtensionP52100046539Registered Aug 2022Delayed 730dExtension1 red flag

Shankeshwar Business Hub Phase 1

A commercial project by Arunita Developers in MOHAMMADWADI, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
7%
cost-weighted
Declared completion
Dec 2027
delayed 730d
Units sold
30 / 43
70% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Arunita Developers · Partnership
Project type
Commercial
Land area
2,100 m² · Permissible built-up (FSI) 11,039 m²
Total units
43 across 1 wing
Estimated cost
₹62.1 Cr
Application date
02 Jul 2022
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA7 of 7 proposed43
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
NITIN B NAIK · CA/90/13530
Structural engineer
PRAVIN M KALAMKAR
Project bank
IDFC First Bank Ltd
Location

Where it sits

MOHAMMADWADI, Pune — 411060.

Locality
MOHAMMADWADI
District
Pune
Authority
Pune Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Shankeshwar Business Hub Phase 1: common questions

Is Shankeshwar Business Hub Phase 1 RERA registered?

Yes. Shankeshwar Business Hub Phase 1 is registered with MahaRERA under registration number P52100046539, granted on 10 August 2022. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Shankeshwar Business Hub Phase 1?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 730 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Shankeshwar Business Hub Phase 1?

Shankeshwar Business Hub Phase 1 is developed by Arunita Developers, the promoter named in its MahaRERA registration.

Where is Shankeshwar Business Hub Phase 1 located?

Shankeshwar Business Hub Phase 1 is in Mohammadwadi, Pune (PIN 411060), Maharashtra, as declared in its RERA registration.

How many units does Shankeshwar Business Hub Phase 1 have, and how many are sold?

Shankeshwar Business Hub Phase 1 has 43 units on its RERA registration. 30 were reported sold as of July 2026, leaving 13 unsold.

How much construction of Shankeshwar Business Hub Phase 1 is complete?

By the developer's own quarterly filing, 7% of the work is done, measured against the project's cost estimate.

Is there any litigation against Shankeshwar Business Hub Phase 1?

No litigation is declared on Shankeshwar Business Hub Phase 1's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.