Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Vedant Dynamic Associates · Partnership
- Project type
- Commercial
- Land area
- 3,157 m² · Permissible built-up (FSI) 678 m²
- Total units
- 38 across 1 wing
- Estimated cost
- ₹17.5 Cr
- Application date
- 10 Aug 2018
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 5 of 5 proposed | 38 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- Vilas Suresh Tarawadi · CA/92/14877
- Structural engineer
- Rajesh Vasudev Mankani · NA
- Project bank
- STATE BANK OF INDIA
Where it sits
Pisoli, Pune — 411048.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Dynamic Imperia Plus A Phase 4A: common questions
Is Dynamic Imperia Plus A Phase 4A RERA registered?
Yes. Dynamic Imperia Plus A Phase 4A is registered with MahaRERA under registration number P52100017545, granted on 24 August 2018. As of July 2026, the registration is active.
What is the possession date of Dynamic Imperia Plus A Phase 4A?
The developer has declared completion by June 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Dynamic Imperia Plus A Phase 4A?
Dynamic Imperia Plus A Phase 4A is developed by Vedant Dynamic Associates, the promoter named in its MahaRERA registration.
Where is Dynamic Imperia Plus A Phase 4A located?
Dynamic Imperia Plus A Phase 4A is in Pisoli, Pune (PIN 411048), Maharashtra, as declared in its RERA registration.
How many units does Dynamic Imperia Plus A Phase 4A have, and how many are sold?
Dynamic Imperia Plus A Phase 4A has 38 units on its RERA registration. 18 were reported sold as of July 2026, leaving 20 unsold.
How much construction of Dynamic Imperia Plus A Phase 4A is complete?
By the developer's own quarterly filing, 36% of the work is done, measured against the project's cost estimate.
Is there any litigation against Dynamic Imperia Plus A Phase 4A?
No litigation is declared on Dynamic Imperia Plus A Phase 4A's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Pisoli
- Advika Phase IV-C · Pune
- Kumar Palmcrest A6 · Pune
- Emerald Green · Pune
- Banka Sapphire · Pune
- Kumar Palmnest · Pune
- Kingston Greens Phase 1 · Pune
- Riva · Pune
- Garden Enclave · Pune