RERA registered projects in Pisoli, Pune
33 projects are registered with MahaRERA in Pisoli, Pune. Of the 10 still under construction, 4 have passed the completion date their builder declared to RERA.
6
Ongoing, on schedule
4
Ongoing, past due date
20
Completed
3
Lapsed or deregistered
More localities in Pune
Most active builders
- Vedant Dynamic Associates7
- Advika Constructions Private Limited4
- Kumar Properties and Promoters Private Limited4
- Vedant Infracon3
- Banka Constructions2
- Nirman Trimurti Developers2
- Tricon Builderss2
- M/s Shri Chintamani Associates1
All projects
Showing 1–33 of 33, newest registrations first.
- Advika Phase IV-CAdvika Constructions Private LimitedPR1260002600100OngoingDec 2030
- Kumar Palmcrest A6Kumar Properties and Promoters Private LimitedP52100081089OngoingMar 2029
- Emerald GreenM/s Shri Chintamani AssociatesPM1260002500169OngoingAug 2028
- Banka SapphireBanka ConstructionsP52100080598OngoingDec 2030
- Savvitri AarcadeShree Sai DevelopersP52100079994OngoingDec 2028
- Advika Phase III - FAdvika Constructions Private LimitedP52100051370CompletedMar 2028
- Kumar PalmnestKumar Properties and Promoters Private LimitedP52100045312In extensionDec 20304.0 years late
- Kumar Palmcrest A5Kumar Properties and Promoters Private LimitedP52100033817CompletedDec 2025
- Brookefield Willows- A2Nirman Trimurti DevelopersP52100028570LapsedJun 2025
- ARV Newtown Phase IIIVedant InfraconP52100027214CompletedJun 2026
- Advika Phase III - EAdvika Constructions Private LimitedP52100022868CompletedJun 2025
- Kumar Palmcrest A4 BuildingKumar Properties and Promoters Private LimitedP52100022295CompletedAug 2023
- Kingston Greens Phase 1Vedant DevelopmentsP52100019471In extensionJun 202718 months late
- Anika ArcadeP52100018361CompletedMay 2019
- Banka Sapphire A WingBanka ConstructionsP52100017790CompletedDec 2024
- Dynamic Imperia Plus A Phase 4AVedant Dynamic AssociatesP52100017545OngoingJun 2028
- Sunshine Hills Phase-II A-5Tricon BuilderssP52100017202CompletedDec 2023
- Dynamic Imperia Plus B Phase 5BVedant Dynamic AssociatesP52100017200LapsedJun 2026
- Dynamic Imperia Plus D Phase 2BVedant Dynamic AssociatesP52100017126CompletedJun 2026
- Dynamic Imperia Plus F Phase 3Vedant Dynamic AssociatesP52100017142CompletedJun 2023
- Dynamic Imperia Plus D Phase 2AVedant Dynamic AssociatesP52100017073CompletedJun 2026
- Dynamic Imperia Plus B Phase 5AVedant Dynamic AssociatesP52100017094CompletedJun 2026
- Dynamic Imperia Plus C Phase 1Vedant Dynamic AssociatesP52100017070CompletedDec 2022
- ARV Newtown Phase IIVedant InfraconP52100015904CompletedDec 2025
- Sunshine Hills Phase 2Tricon BuilderssP52100014445DeregisteredDec 2022
- Advika Phase IIAdvika Constructions Private LimitedP52100013261CompletedDec 2021
- Nobles Heights Building A1 AND A2-Phase 1Golden Palm InfrastructureP52100010046In extensionDec 20296.0 years late
- RivaAsian VenturesP52100004157In extensionNov 20277.1 years late
- ARV NewtownVedant InfraconP52100002738CompletedDec 2021
- ARV Imperia C, D and E BuildingVedant BuildconP52100002415CompletedDec 2018
- Sarthak BelvaSarthak VenturesP52100002181CompletedSept 2022
- Brookefield WillowsNirman Trimurti DevelopersP52100002035CompletedDec 2019
- Gagan Lawish Phase 2Gagan Ace InfraP52100001283CompletedDec 2020