In ExtensionP51700053217Registered Oct 2023Delayed 730dExtension1 red flag

Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3

A residential / group housing project by Adrika Developers Private Limited in Kalher Junction, Bhiwandi, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
21%
cost-weighted
Declared completion
Oct 2030
delayed 730d
Units sold
417 / 682
61% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Adrika Developers Private Limited · Company
Project type
Residential / Group Housing
Land area
6,608 m² · Permissible built-up (FSI) 46,222 m²
Total units
682 across 1 wing
Estimated cost
₹141.5 Cr
Application date
18 Aug 2023
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA33 of 33 proposed682
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Spaceage Consultants
Structural engineer
Paras R Vishwakarma
Project bank
HDFC BANK
Location

Where it sits

Kalher Junction, Bhiwandi, Thane — 421302.

Locality
Kalher Junction, Bhiwandi
District
Thane
Authority
Thane Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3: common questions

Is Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3 RERA registered?

Yes. Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3 is registered with MahaRERA under registration number P51700053217, granted on 23 October 2023. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3?

The developer has declared completion by October 2030 in its MahaRERA filing, revised from the original October 2028. The record shows the project running 730 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3?

Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3 is developed by Adrika Developers Private Limited, the promoter named in its MahaRERA registration.

Where is Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3 located?

Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3 is in Bhiwandi, Thane (PIN 421302), Maharashtra, as declared in its RERA registration.

How many units does Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3 have, and how many are sold?

Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3 has 682 units on its RERA registration. 429 were reported sold as of July 2026, leaving 253 unsold.

How much construction of Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3 is complete?

By the developer's own quarterly filing, 21% of the work is done, measured against the project's cost estimate.

Is there any litigation against Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3?

1 litigation case is declared on Dosti Greater Thane - Sector 3A - Cluster 1B - Phase 3's MahaRERA record. The full report lists each case with its court and status.

More RERA projects in Bhiwandi

All RERA projects in Bhiwandi →

Other projects by Adrika Developers Private Limited

All projects by Adrika Developers Private Limited →