In ExtensionP51900006273Registered Aug 2017Delayed 1614dExtension1 red flag

Dhunjibhoy Ice Factorypvt Ltd

A residential / group housing project by Dhunjibhoy Ice Factory Pvt. Ltd. in MAZGAON, Mumbai City.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
90%
cost-weighted
Declared completion
Dec 2027
delayed 1614d
Units sold
0 / 30
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Dhunjibhoy Ice Factory Pvt. Ltd. · Company
Project type
Residential / Group Housing
Land area
1,075 m² · Permissible built-up (FSI) 6,444 m²
Total units
30 across 1 wing
Estimated cost
₹20.6 Cr
Parking
0 four-wheeler · 1 two-wheeler
Application date
31 Jul 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA10 of 10 proposed30
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
RAJPURKAR ASSOCIATES · M/365/LS
Structural engineer
VIJAY DOSHI · STR/J/44 M30697
Project bank
KOTAK MAHINDRA BANK LIMITED
Location

Where it sits

MAZGAON, Mumbai City — 400010.

Locality
MAZGAON
District
Mumbai City
Authority
MCGM
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

Dhunjibhoy Ice Factorypvt Ltd: common questions

Is Dhunjibhoy Ice Factorypvt Ltd RERA registered?

Yes. Dhunjibhoy Ice Factorypvt Ltd is registered with MahaRERA under registration number P51900006273, granted on 14 August 2017. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Dhunjibhoy Ice Factorypvt Ltd?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original July 2023. The record shows the project running 1614 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Dhunjibhoy Ice Factorypvt Ltd?

Dhunjibhoy Ice Factorypvt Ltd is developed by Dhunjibhoy Ice Factory Pvt. Ltd., the promoter named in its MahaRERA registration.

Where is Dhunjibhoy Ice Factorypvt Ltd located?

Dhunjibhoy Ice Factorypvt Ltd is in Mazgaon, Mumbai (PIN 400010), Maharashtra, as declared in its RERA registration.

How many units does Dhunjibhoy Ice Factorypvt Ltd have, and how many are sold?

Dhunjibhoy Ice Factorypvt Ltd has 30 units on its RERA registration. 0 were reported sold as of July 2026, leaving 30 unsold.

How much construction of Dhunjibhoy Ice Factorypvt Ltd is complete?

By the developer's own quarterly filing, 90% of the work is done, measured against the project's cost estimate.

Is there any litigation against Dhunjibhoy Ice Factorypvt Ltd?

No litigation is declared on Dhunjibhoy Ice Factorypvt Ltd's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.