In ExtensionP52100033449Registered Feb 2022Delayed 944dExtension1 red flag

Chintamani Capital & Vinay Residency

A others project by M/s Varad Vinayak Developers in ERANDWANE, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
50%
cost-weighted
Declared completion
Dec 2027
delayed 944d
Units sold
0 / 80
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
M/s Varad Vinayak Developers · Partnership
Project type
Others
Land area
1,502 m² · Permissible built-up (FSI) 15,349 m²
Total units
80 across 2 wings
Estimated cost
₹47.6 Cr
Land ownership
Promoter is the landowner
Parking
56 four-wheeler · 166 two-wheeler
Held outside open sale
11 landowner/investor share
Application date
10 Feb 2022
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA12 of 12 proposed43
NA12 of 12 proposed37
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
VILAS TARWADI · CA/92/14877
Structural engineer
PARIMAL PAWAR
Project bank
SARASWAT COOPERATIVE BANK LIMITED
Location

Where it sits

ERANDWANE, Pune — 411004.

Locality
ERANDWANE
District
Pune
Authority
SLUM REHABILITATION AUTHORITY PUNE-PIMPRI CHINCHWAD AREA
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

Chintamani Capital & Vinay Residency: common questions

Is Chintamani Capital & Vinay Residency RERA registered?

Yes. Chintamani Capital & Vinay Residency is registered with MahaRERA under registration number P52100033449, granted on 22 February 2022. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Chintamani Capital & Vinay Residency?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original May 2025. The record shows the project running 944 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Chintamani Capital & Vinay Residency?

Chintamani Capital & Vinay Residency is developed by M/s Varad Vinayak Developers, the promoter named in its MahaRERA registration.

Where is Chintamani Capital & Vinay Residency located?

Chintamani Capital & Vinay Residency is in Erandwane, Pune (PIN 411004), Maharashtra, as declared in its RERA registration.

How many units does Chintamani Capital & Vinay Residency have, and how many are sold?

Chintamani Capital & Vinay Residency has 80 units on its RERA registration. 0 were reported sold as of July 2026, leaving 80 unsold.

How much construction of Chintamani Capital & Vinay Residency is complete?

By the developer's own quarterly filing, 50% of the work is done, measured against the project's cost estimate.

Is there any litigation against Chintamani Capital & Vinay Residency?

No litigation is declared on Chintamani Capital & Vinay Residency's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.