Status & progress

Per MahaRERA record as of Jul 2026.

Construction
65%
cost-weighted
Declared completion
Jun 2027
no delay on record
Units sold
57 / 104
55% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Shree Venkatesh Buildcon Pvt Ltd · Company
Project type
Residential / Group Housing
Land area
2,604 m² · Permissible built-up (FSI) 14,244 m²
Total units
104 across 1 wing
Estimated cost
₹80 Cr
Parking
75 four-wheeler · 104 two-wheeler
Application date
25 Dec 2023
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA34 of 34 proposed104
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
T F CUBE DESIGN STUDIO · CA/96/19709
Structural engineer
· EN16-39969
Project bank
INDIAN OVERSEAS BANK
Location

Where it sits

ERANDWANE, Pune — 411004.

Locality
ERANDWANE
District
Pune
Authority
PUNE MUNICIPAL CORPORATION
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Venkatesh Erandwane Central Building A2 Phase 3: common questions

Is Venkatesh Erandwane Central Building A2 Phase 3 RERA registered?

Yes. Venkatesh Erandwane Central Building A2 Phase 3 is registered with MahaRERA under registration number P52100055029, granted on 26 February 2024. As of July 2026, the registration is active.

What is the possession date of Venkatesh Erandwane Central Building A2 Phase 3?

The developer has declared completion by June 2027 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Venkatesh Erandwane Central Building A2 Phase 3?

Venkatesh Erandwane Central Building A2 Phase 3 is developed by Shree Venkatesh Buildcon Pvt Ltd, the promoter named in its MahaRERA registration.

Where is Venkatesh Erandwane Central Building A2 Phase 3 located?

Venkatesh Erandwane Central Building A2 Phase 3 is in Erandwane, Pune (PIN 411004), Maharashtra, as declared in its RERA registration.

How many units does Venkatesh Erandwane Central Building A2 Phase 3 have, and how many are sold?

Venkatesh Erandwane Central Building A2 Phase 3 has 104 units on its RERA registration. 32 were reported sold as of July 2026, leaving 72 unsold.

How much construction of Venkatesh Erandwane Central Building A2 Phase 3 is complete?

By the developer's own quarterly filing, 65% of the work is done, measured against the project's cost estimate.

Is there any litigation against Venkatesh Erandwane Central Building A2 Phase 3?

No litigation is declared on Venkatesh Erandwane Central Building A2 Phase 3's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.