In ExtensionP51800001140Registered Jul 2017Delayed 1826dExtension2 red flags

Avante

A residential / group housing project by Sanjeevani Vyapaar LLP in Kanjur Marg, Mumbai Suburban.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
88%
cost-weighted
Declared completion
Dec 2027
delayed 1826d
Units sold
357 / 383
93% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Sanjeevani Vyapaar LLP · Partnership
Project type
Residential / Group Housing
Land area
7,307 m² · Permissible built-up (FSI) 24,287 m²
Total units
383 across 3 wings
Estimated cost
₹160.7 Cr
Parking
353 four-wheeler · 0 two-wheeler
Application date
21 Jul 2017
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA31 of 31 proposed146
NA30 of 30 proposed140
NA30 of 30 proposed97
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
SANDEEP SHIKRE & ASSOCIATES · CA/98/22945
Structural engineer
Project bank
INDUSIND BANK
Location

Where it sits

Kanjur Marg, Mumbai Suburban — 400078.

Locality
Kanjur Marg
District
Mumbai Suburban
Authority
MCGM
Red flags

2 flags on this project

What they are and why they matter — in the full report.

Unlock the 2 red flags on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Avante: common questions

Is Avante RERA registered?

Yes. Avante is registered with MahaRERA under registration number P51800001140, granted on 26 July 2017. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Avante?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original December 2022. The record shows the project running 1826 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Avante?

Avante is developed by Sanjeevani Vyapaar LLP, the promoter named in its MahaRERA registration.

Where is Avante located?

Avante is in Mumbai (PIN 400078), Maharashtra, as declared in its RERA registration.

How many units does Avante have, and how many are sold?

Avante has 383 units on its RERA registration. 378 were reported sold as of July 2026, leaving 5 unsold.

How much construction of Avante is complete?

By the developer's own quarterly filing, 88% of the work is done, measured against the project's cost estimate.

Is there any litigation against Avante?

1 litigation case is declared on Avante's MahaRERA record. The full report lists each case with its court and status.

RERA projects nearby