In ExtensionP51700029295Registered May 2021Delayed 748dExtension1 red flag

Aditya Matruchaya

A others project by Square Developers in AMBERNATH, Thane.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
95%
cost-weighted
Declared completion
Sept 2026
delayed 748d
Units sold
24 / 56
43% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Square Developers · Partnership
Project type
Others
Land area
881 m² · Permissible built-up (FSI) 3,048 m²
Total units
56 across 1 wing
Estimated cost
₹8.9 Cr
Land ownership
Promoter is the landowner
Held outside open sale
20 landowner/investor share
Application date
28 Apr 2021
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA10 of 10 proposed56
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
JATIN B CHAUDHARI · CA/03/32171
Structural engineer
PRAMOD KAMBLE · STATE/R/2022/APL/00304
Project bank
IDBI BANK
Location

Where it sits

AMBERNATH, Thane — 421501.

Locality
AMBERNATH
District
Thane
Authority
Ambernath Municipal
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

Aditya Matruchaya: common questions

Is Aditya Matruchaya RERA registered?

Yes. Aditya Matruchaya is registered with MahaRERA under registration number P51700029295, granted on 18 May 2021. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Aditya Matruchaya?

The developer has declared completion by September 2026 in its MahaRERA filing, revised from the original September 2024. The record shows the project running 748 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Aditya Matruchaya?

Aditya Matruchaya is developed by Square Developers, the promoter named in its MahaRERA registration.

Where is Aditya Matruchaya located?

Aditya Matruchaya is in Ambernath, Thane (PIN 421501), Maharashtra, as declared in its RERA registration.

How many units does Aditya Matruchaya have, and how many are sold?

Aditya Matruchaya has 56 units on its RERA registration. 27 were reported sold as of September 2026, leaving 29 unsold.

How much construction of Aditya Matruchaya is complete?

By the developer's own quarterly filing, 95% of the work is done, measured against the project's cost estimate.

Is there any litigation against Aditya Matruchaya?

No litigation is declared on Aditya Matruchaya's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Ambernath

All RERA projects in Ambernath →