Merry Mansion
A mixed project by Divya Enterprises in AMBERNATH, Thane.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Divya Enterprises
- Project type
- Mixed
- Land area
- 903 m² · Permissible built-up (FSI) 2,908 m²
- Total units
- 44 across 1 wing
- Estimated cost
- ₹5.6 Cr
- Land ownership
- Promoter is the landowner
- Parking
- 13 four-wheeler · 45 two-wheeler
- Held outside open sale
- 24 landowner/investor share
- Application date
- 22 Dec 2025
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 7 of 7 proposed | 44 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- · CA/2024/174800
- Structural engineer
- ATUL KUDTARKAR AND ASSOCIATES PVT LTD · STATE/R/2025/APL/16827
- Project bank
- FEDERAL BANK
Where it sits
AMBERNATH, Thane — 421501.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Merry Mansion: common questions
Is Merry Mansion RERA registered?
Yes. Merry Mansion is registered with MahaRERA under registration number PM1330002502661, granted on 9 March 2026. As of July 2026, the registration is active.
What is the possession date of Merry Mansion?
The developer has declared completion by May 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Merry Mansion?
Merry Mansion is developed by Divya Enterprises, the promoter named in its MahaRERA registration.
Where is Merry Mansion located?
Merry Mansion is in Ambernath, Thane (PIN 421501), Maharashtra, as declared in its RERA registration.
How many units does Merry Mansion have, and how many are sold?
Merry Mansion has 44 units on its RERA registration. 2 were reported sold as of July 2026, leaving 42 unsold.
How much construction of Merry Mansion is complete?
By the developer's own quarterly filing, 8% of the work is done, measured against the project's cost estimate.
Is there any litigation against Merry Mansion?
No litigation is declared on Merry Mansion's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Ambernath
- Pavillion East View · Thane
- Lakshmi Heights · Thane
- Amber City Centre · Thane
- Derton Crown · Thane
- Mohan Precious Greens Phase III · Thane
- Precious Icon Phase II · Thane
- Innovative Bliss · Thane
- Shree Ram Kutir · Thane