Weone 153
A others project by GRD Infraprojects Private Limited in Wakad, Pune.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- GRD Infraprojects Private Limited · Company
- Project type
- Others
- Land area
- 700 m² · Permissible built-up (FSI) 4,877 m²
- Total units
- 33 across 1 wing
- Estimated cost
- ₹3.9 Cr
- Land ownership
- Promoter is the landowner
- Held outside open sale
- 15 landowner/investor share
- Application date
- 29 Jan 2024
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 5 of 5 proposed | 33 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- Design Associates · PCMC/LE/05382017
- Structural engineer
- Avinash Salunkhe
- Project bank
- ICICI BANK LIMITED
Where it sits
Wakad, Pune — 411057.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Weone 153: common questions
Is Weone 153 RERA registered?
Yes. Weone 153 is registered with MahaRERA under registration number P52100054963, granted on 21 February 2024. As of July 2026, the registration is active.
What is the possession date of Weone 153?
The developer has declared completion by December 2026 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Weone 153?
Weone 153 is developed by GRD Infraprojects Private Limited, the promoter named in its MahaRERA registration.
Where is Weone 153 located?
Weone 153 is in Wakad, Pune (PIN 411057), Maharashtra, as declared in its RERA registration.
How many units does Weone 153 have, and how many are sold?
Weone 153 has 33 units on its RERA registration. 25 were reported sold as of July 2026, leaving 8 unsold.
How much construction of Weone 153 is complete?
By the developer's own quarterly filing, 32% of the work is done, measured against the project's cost estimate.
Is there any litigation against Weone 153?
No litigation is declared on Weone 153's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Wakad
- Arise Capital · Pune
- Millefiori · Pune
- Meridian Studios · Pune
- The Raya Phase I · Pune
- Truston Aspen · Pune
- Highness · Pune
- Luxton · Pune
- Kohinoor Regalia Towers · Pune
Other projects by GRD Infraprojects Private Limited
- Westfield 3 · Pune
- Weone 121 · Pune