In ExtensionP51800046901Registered Sept 2022Delayed 365dExtension1 red flag

Valletta

A residential / group housing project by K Raheja Corp Real Estate Private Limited in VILE PARLE WEST, Mumbai Suburban.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
79%
cost-weighted
Declared completion
Sept 2026
delayed 365d
Units sold
17 / 25
68% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
K Raheja Corp Real Estate Private Limited · Company
Project type
Residential / Group Housing
Land area
2,200 m² · Permissible built-up (FSI) 8,300 m²
Total units
25 across 1 wing
Estimated cost
₹72.7 Cr
Parking
72 four-wheeler · 0 two-wheeler
Application date
30 Aug 2022
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA16 of 16 proposed25
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
· CA/83/7386
Structural engineer
· S/927/SS-J
Project bank
STANDARD CHARTERED BANK
Location

Where it sits

VILE PARLE WEST, Mumbai Suburban — 400049.

Locality
VILE PARLE WEST
District
Mumbai Suburban
Authority
CE/9084/WS/AK
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Valletta: common questions

Is Valletta RERA registered?

Yes. Valletta is registered with MahaRERA under registration number P51800046901, granted on 16 September 2022. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Valletta?

The developer has declared completion by September 2026 in its MahaRERA filing, revised from the original September 2025. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Valletta?

Valletta is developed by K Raheja Corp Real Estate Private Limited, the promoter named in its MahaRERA registration.

Where is Valletta located?

Valletta is in Vile Parle West, Mumbai (PIN 400049), Maharashtra, as declared in its RERA registration.

How many units does Valletta have, and how many are sold?

Valletta has 25 units on its RERA registration. 11 were reported sold as of July 2026, leaving 14 unsold.

How much construction of Valletta is complete?

By the developer's own quarterly filing, 79% of the work is done, measured against the project's cost estimate.

Is there any litigation against Valletta?

3 litigation cases are declared on Valletta's MahaRERA record. The full report lists each case with its court and status.