In ExtensionP51700020227Registered Mar 2019Delayed 1297dExtension1 red flag

Tycoons Orbis

A others project by M/s. Tycoons Developers in Kalyan, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
44%
mean of activity checklist
Declared completion
Dec 2026
delayed 1297d
Units sold
80 / 333
24% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
M/s. Tycoons Developers · Partnership
Project type
Others
Land area
6,780 m² · Permissible built-up (FSI) 16,823 m²
Total units
333 across 2 wings
Land ownership
Promoter is the landowner
Held outside open sale
141 rehab
Application date
28 Mar 2019
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA21 of 21 proposed153
NA22 of 22 proposed180
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Ms Design Waves
Structural engineer
Mr Mandar Bharat Salvi
Project bank
HDFC BANK
Location

Where it sits

Kalyan, Thane — 421301.

Locality
Kalyan
District
Thane
Authority
Kalyan Dombivali Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Tycoons Orbis: common questions

Is Tycoons Orbis RERA registered?

Yes. Tycoons Orbis is registered with MahaRERA under registration number P51700020227, granted on 29 March 2019. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Tycoons Orbis?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original June 2023. The record shows the project running 1297 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Tycoons Orbis?

Tycoons Orbis is developed by M/s. Tycoons Developers, the promoter named in its MahaRERA registration.

Where is Tycoons Orbis located?

Tycoons Orbis is in Kalyan, Thane (PIN 421301), Maharashtra, as declared in its RERA registration.

How many units does Tycoons Orbis have, and how many are sold?

Tycoons Orbis has 333 units on its RERA registration. 98 were reported sold as of July 2026, leaving 235 unsold.

Is there any litigation against Tycoons Orbis?

No litigation is declared on Tycoons Orbis's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Kalyan

All RERA projects in Kalyan →