In ExtensionP51800003235Registered Aug 2017Delayed 2922dExtension1 red flag

Tivon Park Wing E and F

A residential / group housing project by D S Developers in Ghatkopar-(west), Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
110%
cost-weighted
Declared completion
Dec 2026
delayed 2922d
Units sold
54 / 54
100% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
D S Developers · Partnership
Project type
Residential / Group Housing
Land area
511 m² · Permissible built-up (FSI) 4,017 m²
Total units
54 across 1 wing
Estimated cost
₹23.7 Cr
Application date
28 Jul 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA11 of 11 proposed54
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Manoj V Daisaria · CA/82/7254
Structural engineer
Project bank
HDFC BANK
Location

Where it sits

Ghatkopar-(west), Mumbai Suburban — 400086.

Locality
Ghatkopar-(west)
District
Mumbai Suburban
Authority
Brihanmumbai Muncipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Tivon Park Wing E and F: common questions

Is Tivon Park Wing E and F RERA registered?

Yes. Tivon Park Wing E and F is registered with MahaRERA under registration number P51800003235, granted on 5 August 2017. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Tivon Park Wing E and F?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original December 2018. The record shows the project running 2922 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Tivon Park Wing E and F?

Tivon Park Wing E and F is developed by D S Developers, the promoter named in its MahaRERA registration.

Where is Tivon Park Wing E and F located?

Tivon Park Wing E and F is in Ghatkopar West, Mumbai (PIN 400086), Maharashtra, as declared in its RERA registration.

How many units does Tivon Park Wing E and F have, and how many are sold?

Tivon Park Wing E and F has 54 units on its RERA registration. 54 were reported sold as of September 2026, leaving 0 unsold.

How much construction of Tivon Park Wing E and F is complete?

By the developer's own quarterly filing, 110% of the work is done, measured against the project's cost estimate.

Is there any litigation against Tivon Park Wing E and F?

No litigation is declared on Tivon Park Wing E and F's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.