In ExtensionP52100045231Registered May 2022Delayed 225dExtension1 red flag

The Camelia Phase - 1

A others project by Akanksha Builders in Wakad, Pune.

Data as of Oct 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Oct 2026.

Construction
83%
cost-weighted
Declared completion
Jan 2027
delayed 225d
Units sold
305 / 426
72% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Akanksha Builders · Partnership
Project type
Others
Land area
8,153 m² · Permissible built-up (FSI) 40,698 m²
Total units
426 across 3 wings
Estimated cost
₹125.4 Cr
Land ownership
Promoter is the landowner
Application date
03 May 2022
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA21 of 21 proposed124
NA21 of 21 proposed218
NA22 of 22 proposed84
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
ANA Consortium Pvt Ld · CA/89/11974
Structural engineer
S K Consultants & Engineers · STATE/R/2024/APL/14306
Project bank
AXIS BANK
Location

Where it sits

Wakad, Pune — 411057.

Locality
Wakad
District
Pune
Authority
Pimpri Chinchwad Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

The Camelia Phase - 1: common questions

Is The Camelia Phase - 1 RERA registered?

Yes. The Camelia Phase - 1 is registered with MahaRERA under registration number P52100045231, granted on 10 May 2022. As of October 2026, the registration is active under a MahaRERA extension.

What is the possession date of The Camelia Phase - 1?

The developer has declared completion by January 2027 in its MahaRERA filing, revised from the original June 2026. The record shows the project running 225 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of The Camelia Phase - 1?

The Camelia Phase - 1 is developed by Akanksha Builders, the promoter named in its MahaRERA registration.

Where is The Camelia Phase - 1 located?

The Camelia Phase - 1 is in Wakad, Pune (PIN 411057), Maharashtra, as declared in its RERA registration.

How many units does The Camelia Phase - 1 have, and how many are sold?

The Camelia Phase - 1 has 426 units on its RERA registration. 325 were reported sold as of October 2026, leaving 101 unsold.

How much construction of The Camelia Phase - 1 is complete?

By the developer's own quarterly filing, 83% of the work is done, measured against the project's cost estimate.

Is there any litigation against The Camelia Phase - 1?

No litigation is declared on The Camelia Phase - 1's MahaRERA record as of October 2026. A clean record reflects what was filed, not a legal title check.