ActiveP51900050381Registered Apr 20232 red flags

The Altitude

A residential / group housing project by VDV Infrastructures LLP in Tardeo, Mumbai City.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
12%
cost-weighted
Declared completion
Mar 2029
no delay on record
Units sold
0 / 149
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
VDV Infrastructures LLP · Partnership
Project type
Residential / Group Housing
Land area
1,211 m² · Permissible built-up (FSI) 11,681 m²
Total units
149 across 1 wing
Estimated cost
₹20 Cr
Held outside open sale
93 rehab
Application date
10 Jan 2023
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA28 of 28 proposed149
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
1 Architectural Consultant · S/526/LS
Structural engineer
Architectural Consultant · S/526/LS
Project bank
Location

Where it sits

Tardeo, Mumbai City — 400034.

Locality
Tardeo
District
Mumbai City
Authority
EB/6703/D/A
Red flags

2 flags on this project

What they are and why they matter — in the full report.

Unlock the 2 red flags on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

The Altitude: common questions

Is The Altitude RERA registered?

Yes. The Altitude is registered with MahaRERA under registration number P51900050381, granted on 5 April 2023. As of July 2026, the registration is active.

What is the possession date of The Altitude?

The developer has declared completion by March 2029 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of The Altitude?

The Altitude is developed by VDV Infrastructures LLP, the promoter named in its MahaRERA registration.

Where is The Altitude located?

The Altitude is in Tardeo, Mumbai (PIN 400034), Maharashtra, as declared in its RERA registration.

How many units does The Altitude have, and how many are sold?

The Altitude has 149 units on its RERA registration. 0 were reported sold as of July 2026, leaving 149 unsold.

How much construction of The Altitude is complete?

By the developer's own quarterly filing, 12% of the work is done, measured against the project's cost estimate.

Is there any litigation against The Altitude?

No litigation is declared on The Altitude's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Tardeo

All RERA projects in Tardeo →