In ExtensionP51800030947Registered Sept 2021Delayed 730dExtension1 red flag

Sunteck Pinnacle 1

A commercial project by Sunteck Realty Limited in Ram Mandir Road, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
100%
cost-weighted
Declared completion
Dec 2027
delayed 730d
Units sold
83 / 127
65% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Sunteck Realty Limited · Company
Project type
Commercial
Land area
2,086 m² · Permissible built-up (FSI) 7,175 m²
Total units
127 across 1 wing
Estimated cost
₹33.8 Cr
Parking
194 four-wheeler · 0 two-wheeler
Held outside open sale
12 reserved
Application date
23 Sept 2021
Buildings & units

null

Floors and unit counts as filed.

WingFloors sanctionedTotal units
null22 of 22 proposed127
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Sandeep Shikre & Associates · CA/98/22945
Structural engineer
· 98021
Project bank
RBL Bank Limited
Location

Where it sits

Ram Mandir Road, Mumbai Suburban — 400104.

Locality
Ram Mandir Road
District
Mumbai Suburban
Authority
The Mumbai Metropolitan Region Development Authority (MMRDA)
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Sunteck Pinnacle 1: common questions

Is Sunteck Pinnacle 1 RERA registered?

Yes. Sunteck Pinnacle 1 is registered with MahaRERA under registration number P51800030947, granted on 29 September 2021. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Sunteck Pinnacle 1?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 730 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Sunteck Pinnacle 1?

Sunteck Pinnacle 1 is developed by Sunteck Realty Limited, the promoter named in its MahaRERA registration.

Where is Sunteck Pinnacle 1 located?

Sunteck Pinnacle 1 is in Ram Mandir Road, Mumbai (PIN 400104), Maharashtra, as declared in its RERA registration.

How many units does Sunteck Pinnacle 1 have, and how many are sold?

Sunteck Pinnacle 1 has 127 units on its RERA registration. 67 were reported sold as of September 2026, leaving 60 unsold.

How much construction of Sunteck Pinnacle 1 is complete?

By the developer's own quarterly filing, 100% of the work is done, measured against the project's cost estimate.

Is there any litigation against Sunteck Pinnacle 1?

No litigation is declared on Sunteck Pinnacle 1's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Ram Mandir Road

All RERA projects in Ram Mandir Road →