In ExtensionP51800053945Registered Dec 2023Delayed 730dExtension1 red flag

Sugee Vaayu

A others project by Sugee Developers Private Limited in Mulund (W), Mumbai, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
3%
cost-weighted
Declared completion
Dec 2031
delayed 730d
Units sold
0 / 546
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Sugee Developers Private Limited · Company
Project type
Others
Land area
10,071 m² · Permissible built-up (FSI) 52,372 m²
Total units
546 across 2 wings
Estimated cost
₹540 Cr
Parking
710 four-wheeler · 0 two-wheeler
Application date
09 Nov 2023
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA56 of 56 proposed388
NA31 of 31 proposed158
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Mr. Sanjay Neve of M/s. Sanjay Neve & Associates · CA/84/8433
Structural engineer
Mr. Ravindra Dattatraya Deshpande
Project bank
STATE BANK OF INDIA
Location

Where it sits

Mulund (W), Mumbai, Mumbai Suburban — 400078.

Locality
Mulund (W), Mumbai
District
Mumbai Suburban
Authority
Slum Rehabilitation Authority, Mumbai
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Sugee Vaayu: common questions

Is Sugee Vaayu RERA registered?

Yes. Sugee Vaayu is registered with MahaRERA under registration number P51800053945, granted on 11 December 2023. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Sugee Vaayu?

The developer has declared completion by December 2031 in its MahaRERA filing, revised from the original December 2029. The record shows the project running 730 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Sugee Vaayu?

Sugee Vaayu is developed by Sugee Developers Private Limited, the promoter named in its MahaRERA registration.

Where is Sugee Vaayu located?

Sugee Vaayu is in Mulund West, Mumbai (PIN 400078), Maharashtra, as declared in its RERA registration.

How many units does Sugee Vaayu have, and how many are sold?

Sugee Vaayu has 546 units on its RERA registration. 0 were reported sold as of September 2026, leaving 546 unsold.

How much construction of Sugee Vaayu is complete?

By the developer's own quarterly filing, 3% of the work is done, measured against the project's cost estimate.

Is there any litigation against Sugee Vaayu?

No litigation is declared on Sugee Vaayu's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.