In ExtensionP52100004898Registered Aug 2017Delayed 1614dExtension1 red flag

Songs From The Wood - Phase 1

A residential / group housing project by Total Environment Building Systems Private Limited in Uday Baug, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
46%
cost-weighted
Declared completion
Dec 2027
delayed 1614d
Units sold
29 / 80
36% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Total Environment Building Systems Private Limited · Company
Project type
Residential / Group Housing
Land area
13,710 m² · Permissible built-up (FSI) 19,266 m²
Total units
80 across 1 wing
Estimated cost
₹191.4 Cr
Land ownership
Promoter is the landowner
Parking
96 four-wheeler · 240 two-wheeler
Held outside open sale
27 landowner/investor share
Application date
31 Jul 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA28 of 28 proposed80
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Sameer Valimbe
Structural engineer
Surendra Kumar Sagar
Project bank
INDUSIND BANK
Location

Where it sits

Uday Baug, Pune — 411013.

Locality
Uday Baug
District
Pune
Authority
Pune Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Songs From The Wood - Phase 1: common questions

Is Songs From The Wood - Phase 1 RERA registered?

Yes. Songs From The Wood - Phase 1 is registered with MahaRERA under registration number P52100004898, granted on 9 August 2017. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Songs From The Wood - Phase 1?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original July 2023. The record shows the project running 1614 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Songs From The Wood - Phase 1?

Songs From The Wood - Phase 1 is developed by Total Environment Building Systems Private Limited, the promoter named in its MahaRERA registration.

Where is Songs From The Wood - Phase 1 located?

Songs From The Wood - Phase 1 is in Uday Baug, Pune (PIN 411013), Maharashtra, as declared in its RERA registration.

How many units does Songs From The Wood - Phase 1 have, and how many are sold?

Songs From The Wood - Phase 1 has 80 units on its RERA registration. 31 were reported sold as of July 2026, leaving 49 unsold.

How much construction of Songs From The Wood - Phase 1 is complete?

By the developer's own quarterly filing, 46% of the work is done, measured against the project's cost estimate.

Is there any litigation against Songs From The Wood - Phase 1?

No litigation is declared on Songs From The Wood - Phase 1's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.