ActiveP52100079769Registered Mar 2025No active red flags

Skyrena

A mixed project by M.D Developers in Manjari Bk, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
17%
cost-weighted
Declared completion
Feb 2028
no delay on record
Units sold
4 / 22
18% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
M.D Developers · Partnership
Project type
Mixed
Land area
1,714 m² · Permissible built-up (FSI) 2,291 m²
Total units
22 across 1 wing
Estimated cost
₹9.8 Cr
Parking
20 four-wheeler · 59 two-wheeler
Application date
07 Feb 2025
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA5 of 5 proposed22
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Arpan Architects · CA/2018/91882
Structural engineer
MK Construction · PMC/STE/2197/19
Project bank
BANK OF MAHARASHTRA
Location

Where it sits

Manjari Bk, Pune — 412307.

Locality
Manjari Bk
District
Pune
Authority
Pune metropolitan Region Development Authority, Pune
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Skyrena: common questions

Is Skyrena RERA registered?

Yes. Skyrena is registered with MahaRERA under registration number P52100079769, granted on 26 March 2025. As of July 2026, the registration is active.

What is the possession date of Skyrena?

The developer has declared completion by February 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Skyrena?

Skyrena is developed by M.D Developers, the promoter named in its MahaRERA registration.

Where is Skyrena located?

Skyrena is in Manjari Budruk, Pune (PIN 412307), Maharashtra, as declared in its RERA registration.

How many units does Skyrena have, and how many are sold?

Skyrena has 23 units on its RERA registration. 4 were reported sold as of July 2026, leaving 19 unsold.

How much construction of Skyrena is complete?

By the developer's own quarterly filing, 17% of the work is done, measured against the project's cost estimate.

Is there any litigation against Skyrena?

No litigation is declared on Skyrena's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.