Skylark
A residential / group housing project by GL Properties in BORHADEWADI, Pune.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- GL Properties · Partnership
- Project type
- Residential / Group Housing
- Land area
- 1,006 m² · Permissible built-up (FSI) 3,621 m²
- Total units
- 37 across 1 wing
- Estimated cost
- ₹8.9 Cr
- Land ownership
- Promoter is the landowner
- Parking
- 9 four-wheeler · 0 two-wheeler
- Held outside open sale
- 4 landowner/investor share
- Application date
- 21 Dec 2021
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 9 of 9 proposed | 37 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- VINAY SUDAM KUNJIR · PCMC/LE/0001/2000
- Structural engineer
- AJINKYA MAPARI
- Project bank
- TJSB SAHAKARI BANK LTD
Where it sits
BORHADEWADI, Pune — 412105.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Skylark: common questions
Is Skylark RERA registered?
Yes. Skylark is registered with MahaRERA under registration number P52100032865, granted on 2 February 2022. As of July 2026, the registration is active.
What is the possession date of Skylark?
The developer has declared completion by December 2026 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Skylark?
Skylark is developed by GL Properties, the promoter named in its MahaRERA registration.
Where is Skylark located?
Skylark is in Borhadewadi, Pune (PIN 412105), Maharashtra, as declared in its RERA registration.
How many units does Skylark have, and how many are sold?
Skylark has 37 units on its RERA registration. 12 were reported sold as of July 2026, leaving 25 unsold.
How much construction of Skylark is complete?
By the developer's own quarterly filing, 49% of the work is done, measured against the project's cost estimate.
Is there any litigation against Skylark?
No litigation is declared on Skylark's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Borhadewadi
- Sanskriti · Pune
- Vipul Commercial · Pune
- Amrut Bliss · Pune
- K K Tathastu · Pune
- SMH Nakshatra · Pune
- Spring Gardens Phase-III · Pune
- Rajput Ekyum · Pune
- Mangalam Miraya · Pune