ActiveP52100052969Registered Oct 20231 red flag

Skyi Iris, RaceCourse Phase I

A residential / group housing project by Enerrgia Skyi Landmarks in Wanawadi, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
3%
cost-weighted
Declared completion
Jun 2027
no delay on record
Units sold
0 / 40
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Enerrgia Skyi Landmarks · Partnership
Project type
Residential / Group Housing
Land area
3,990 m² · Permissible built-up (FSI) 6,175 m²
Total units
40 across 1 wing
Estimated cost
₹16.8 Cr
Land ownership
Promoter is the landowner
Parking
0 four-wheeler · 13 two-wheeler
Application date
20 Sept 2023
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA11 of 11 proposed40
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
ANA Consortium Pvt Ltd
Structural engineer
Sandeep Rangdal & Asso
Project bank
HDFC BANK
Location

Where it sits

Wanawadi, Pune — 411040.

Locality
Wanawadi
District
Pune
Authority
Pune Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

Skyi Iris, RaceCourse Phase I: common questions

Is Skyi Iris, RaceCourse Phase I RERA registered?

Yes. Skyi Iris, RaceCourse Phase I is registered with MahaRERA under registration number P52100052969, granted on 6 October 2023. As of July 2026, the registration is active.

What is the possession date of Skyi Iris, RaceCourse Phase I?

The developer has declared completion by June 2027 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Skyi Iris, RaceCourse Phase I?

Skyi Iris, RaceCourse Phase I is developed by Enerrgia Skyi Landmarks, the promoter named in its MahaRERA registration.

Where is Skyi Iris, RaceCourse Phase I located?

Skyi Iris, RaceCourse Phase I is in Wanawadi, Pune (PIN 411040), Maharashtra, as declared in its RERA registration.

How many units does Skyi Iris, RaceCourse Phase I have, and how many are sold?

Skyi Iris, RaceCourse Phase I has 40 units on its RERA registration. 0 were reported sold as of July 2026, leaving 40 unsold.

How much construction of Skyi Iris, RaceCourse Phase I is complete?

By the developer's own quarterly filing, 3% of the work is done, measured against the project's cost estimate.

Is there any litigation against Skyi Iris, RaceCourse Phase I?

No litigation is declared on Skyi Iris, RaceCourse Phase I's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Wanawadi

All RERA projects in Wanawadi →

Other projects by Enerrgia Skyi Landmarks

All projects by Enerrgia Skyi Landmarks →