In ExtensionP52100056436Registered May 2024Delayed 1095dExtensionNo active red flags

Silver Meteor

A others project by Roshan Builders LLP in -, Pune.

Data as of Oct 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Oct 2026.

Construction
19%
cost-weighted
Declared completion
Dec 2031
delayed 1095d
Units sold
141 / 571
25% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Roshan Builders LLP · Company
Project type
Others
Land area
23,700 m² · Permissible built-up (FSI) 1,13,424 m²
Total units
571 across 5 wings
Estimated cost
₹295.6 Cr
Land ownership
Promoter is the landowner
Parking
78 four-wheeler · 0 two-wheeler
Held outside open sale
62 landowner/investor share
Application date
15 Apr 2024
Buildings & units

5 wings across 5 buildings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA4 of 4 proposed157
NA4 of 4 proposed1
NA9 of 9 proposed1
NA32 of 32 proposed269
NA40 of 40 proposed143
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
UNUSUAI. SPACES · CA/95/18039
Structural engineer
HANSAL PARIKH
Project bank
ICICI BANK LIMITED
Location

Where it sits

-, Pune — 411033.

Locality
-
District
Pune
Authority
Pimpri Chinchwad Municipal Corporation
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Silver Meteor: common questions

Is Silver Meteor RERA registered?

Yes. Silver Meteor is registered with MahaRERA under registration number P52100056436, granted on 31 May 2024. As of October 2026, the registration is active under a MahaRERA extension.

What is the possession date of Silver Meteor?

The developer has declared completion by December 2031 in its MahaRERA filing, revised from the original December 2028. The record shows the project running 1095 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Silver Meteor?

Silver Meteor is developed by Roshan Builders LLP, the promoter named in its MahaRERA registration.

Where is Silver Meteor located?

Silver Meteor is in Pune (PIN 411033), Maharashtra, as declared in its RERA registration.

How many units does Silver Meteor have, and how many are sold?

Silver Meteor has 571 units on its RERA registration. 221 were reported sold as of October 2026, leaving 350 unsold.

How much construction of Silver Meteor is complete?

By the developer's own quarterly filing, 19% of the work is done, measured against the project's cost estimate.

Is there any litigation against Silver Meteor?

No litigation is declared on Silver Meteor's MahaRERA record as of October 2026. A clean record reflects what was filed, not a legal title check.

RERA projects nearby