ActiveP51900021040Registered May 20191 red flag

Siddha Sky Phase 2

A others project by M/s Sejal Shakti Realtors LLP in Raoli Camp, Kokari Agar, Sadar Nagar No. 4, Near GTB Monorail Station, Sion Koliwada., Mumbai City.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
62%
cost-weighted
Declared completion
Dec 2026
no delay on record
Units sold
324 / 369
88% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
M/s Sejal Shakti Realtors LLP · Others
Project type
Others
Land area
996 m² · Permissible built-up (FSI) 27,560 m²
Total units
369 across 1 wing
Estimated cost
₹158.8 Cr
Application date
23 May 2019
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA46 of 46 proposed369
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
DOT Architects · CA/2004/33829
Structural engineer
Arijit Malik
Project bank
INDUSIND BANK
Location

Where it sits

Raoli Camp, Kokari Agar, Sadar Nagar No. 4, Near GTB Monorail Station, Sion Koliwada., Mumbai City — 400037.

Locality
Raoli Camp, Kokari Agar, Sadar Nagar No. 4, Near GTB Monorail Station, Sion Koliwada.
District
Mumbai City
Authority
Slum Rehabilitation Authority
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Siddha Sky Phase 2: common questions

Is Siddha Sky Phase 2 RERA registered?

Yes. Siddha Sky Phase 2 is registered with MahaRERA under registration number P51900021040, granted on 31 May 2019. As of July 2026, the registration is active.

What is the possession date of Siddha Sky Phase 2?

The developer has declared completion by December 2026 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Siddha Sky Phase 2?

Siddha Sky Phase 2 is developed by M/s Sejal Shakti Realtors LLP, the promoter named in its MahaRERA registration.

Where is Siddha Sky Phase 2 located?

Siddha Sky Phase 2 is in Sion Koliwada., Mumbai (PIN 400037), Maharashtra, as declared in its RERA registration.

How many units does Siddha Sky Phase 2 have, and how many are sold?

Siddha Sky Phase 2 has 369 units on its RERA registration. 330 were reported sold as of July 2026, leaving 39 unsold.

How much construction of Siddha Sky Phase 2 is complete?

By the developer's own quarterly filing, 62% of the work is done, measured against the project's cost estimate.

Is there any litigation against Siddha Sky Phase 2?

No litigation is declared on Siddha Sky Phase 2's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.