Status & progress

Per MahaRERA record as of Jul 2026.

Construction
0%
cost-weighted
Declared completion
Dec 2028
no delay on record
Units sold
0 / 77
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
M/s Rushabh Developers · Partnership
Project type
Mixed
Land area
18,443 m² · Permissible built-up (FSI) 32,427 m²
Total units
77 across 3 wings
Estimated cost
₹119.8 Cr
Land ownership
Third-party landowner declared
Parking
286 four-wheeler · 0 two-wheeler
Held outside open sale
17 landowner/investor share
Application date
26 Sept 2024
Buildings & units

wing C & wing D & wing E

Floors and unit counts as filed.

WingFloors sanctionedTotal units
wing C9 of 24 proposed32
wing D9 of 24 proposed32
wing E4 of 23 proposed13
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
H.M.Jhaveri & Sons · CA/77/3887
Structural engineer
· 840024434
Project bank
HDFC BANK
Location

Where it sits

Malad East, Mumbai Suburban — 400097.

Locality
Malad East
District
Mumbai Suburban
Authority
CHE/7237/BP(WS)/AP
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Shreeji Tapovan: common questions

Is Shreeji Tapovan RERA registered?

Yes. Shreeji Tapovan is registered with MahaRERA under registration number PM1180002400073, granted on 8 October 2024. As of July 2026, the registration is active.

What is the possession date of Shreeji Tapovan?

The developer has declared completion by December 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Shreeji Tapovan?

Shreeji Tapovan is developed by M/s Rushabh Developers, the promoter named in its MahaRERA registration.

Where is Shreeji Tapovan located?

Shreeji Tapovan is in Malad East, Mumbai (PIN 400097), Maharashtra, as declared in its RERA registration.

How many units does Shreeji Tapovan have, and how many are sold?

Shreeji Tapovan has 77 units on its RERA registration. 0 were reported sold as of July 2026, leaving 77 unsold.

How much construction of Shreeji Tapovan is complete?

By the developer's own quarterly filing, 0% of the work is done, measured against the project's cost estimate.

Is there any litigation against Shreeji Tapovan?

1 litigation case is declared on Shreeji Tapovan's MahaRERA record. The full report lists each case with its court and status.