In ExtensionP52100047346Registered Oct 2022Delayed 365dExtensionNo active red flags

Shree Saai Forrtune

A others project by Mrunali Realty LLP in Gat No 49P 50/1 P, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
57%
cost-weighted
Declared completion
Dec 2027
delayed 365d
Units sold
106 / 281
38% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Mrunali Realty LLP · Others
Project type
Others
Land area
8,997 m² · Permissible built-up (FSI) 26,696 m²
Total units
281 across 3 wings
Estimated cost
₹89.8 Cr
Land ownership
Promoter is the landowner
Parking
684 four-wheeler · 393 two-wheeler
Held outside open sale
13 landowner/investor share
Application date
10 Sept 2022
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA14 of 14 proposed143
NA14 of 14 proposed106
NA6 of 10 proposed32
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Ar Sandeep Khatpe · CA/9722035
Structural engineer
Mr Rahul Bhandari · No
Project bank
HDFC BANK
Location

Where it sits

Gat No 49P 50/1 P, Pune — 411015.

Locality
Gat No 49P 50/1 P
District
Pune
Authority
Pimpri Chinchwad Municipal Corporation
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Shree Saai Forrtune: common questions

Is Shree Saai Forrtune RERA registered?

Yes. Shree Saai Forrtune is registered with MahaRERA under registration number P52100047346, granted on 20 October 2022. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Shree Saai Forrtune?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original December 2026. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Shree Saai Forrtune?

Shree Saai Forrtune is developed by Mrunali Realty LLP, the promoter named in its MahaRERA registration.

Where is Shree Saai Forrtune located?

Shree Saai Forrtune is in Pune (PIN 411015), Maharashtra, as declared in its RERA registration.

How many units does Shree Saai Forrtune have, and how many are sold?

Shree Saai Forrtune has 281 units on its RERA registration. 178 were reported sold as of July 2026, leaving 103 unsold.

How much construction of Shree Saai Forrtune is complete?

By the developer's own quarterly filing, 57% of the work is done, measured against the project's cost estimate.

Is there any litigation against Shree Saai Forrtune?

No litigation is declared on Shree Saai Forrtune's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

RERA projects nearby