ActivePR1330002501695Registered Dec 2025No active red flags

Sarvoday Patwardhan Baug - Building No 2

A residential / group housing project by Sarvoday Developers in Kalyan West, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
33%
cost-weighted
Declared completion
Dec 2028
no delay on record
Units sold
0 / 210
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Sarvoday Developers · Partnership
Project type
Residential / Group Housing
Land area
14,340 m² · Permissible built-up (FSI) 19,903 m²
Total units
210 across 3 wings
Estimated cost
₹46.8 Cr
Land ownership
Promoter is the landowner
Parking
60 four-wheeler · 0 two-wheeler
Held outside open sale
4 landowner/investor share
Application date
07 Nov 2025
Buildings & units

Wing - A & Wing - B & Wing - C

Floors and unit counts as filed.

WingFloors sanctionedTotal units
Wing - A13 of 13 proposed70
Wing - B13 of 13 proposed70
Wing - C13 of 13 proposed70
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Rachana Arch · CA/2002/28737
Structural engineer
Shanti Consultant · STATE/R/2024/APL/10850
Project bank
BANDHAN BANK LIMITED
Location

Where it sits

Kalyan West, Thane — 421201.

Locality
Kalyan West
District
Thane
Authority
Kalyan Dombivali Municipal Corporation
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Sarvoday Patwardhan Baug - Building No 2: common questions

Is Sarvoday Patwardhan Baug - Building No 2 RERA registered?

Yes. Sarvoday Patwardhan Baug - Building No 2 is registered with MahaRERA under registration number PR1330002501695, granted on 5 December 2025. As of July 2026, the registration is active.

What is the possession date of Sarvoday Patwardhan Baug - Building No 2?

The developer has declared completion by December 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Sarvoday Patwardhan Baug - Building No 2?

Sarvoday Patwardhan Baug - Building No 2 is developed by Sarvoday Developers, the promoter named in its MahaRERA registration.

Where is Sarvoday Patwardhan Baug - Building No 2 located?

Sarvoday Patwardhan Baug - Building No 2 is in Kalyan West, Thane (PIN 421201), Maharashtra, as declared in its RERA registration.

How many units does Sarvoday Patwardhan Baug - Building No 2 have, and how many are sold?

Sarvoday Patwardhan Baug - Building No 2 has 210 units on its RERA registration. 0 were reported sold as of July 2026, leaving 210 unsold.

How much construction of Sarvoday Patwardhan Baug - Building No 2 is complete?

By the developer's own quarterly filing, 33% of the work is done, measured against the project's cost estimate.

Is there any litigation against Sarvoday Patwardhan Baug - Building No 2?

No litigation is declared on Sarvoday Patwardhan Baug - Building No 2's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Kalyan West

All RERA projects in Kalyan West →