Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Ami Modispaces LLP · Partnership
- Project type
- Residential / Group Housing
- Land area
- 1,600 m² · Permissible built-up (FSI) 8,640 m²
- Total units
- 133 across 2 wings
- Estimated cost
- ₹68.6 Cr
- Held outside open sale
- 56 reserved
- Application date
- 06 Jan 2025
2 wings
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 31 of 31 proposed | 50 |
| NA | 33 of 33 proposed | 83 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- Rahul Kamathi · CA 2000/26182
- Structural engineer
- Ajay Pandurang Gade
- Project bank
- ICICI BANK LIMITED
Where it sits
Borivali, Mumbai Suburban — 400092.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Ruparel Zinnia: common questions
Is Ruparel Zinnia RERA registered?
Yes. Ruparel Zinnia is registered with MahaRERA under registration number P51800079098, granted on 5 February 2025. As of July 2026, the registration is active.
What is the possession date of Ruparel Zinnia?
The developer has declared completion by June 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Ruparel Zinnia?
Ruparel Zinnia is developed by Ami Modispaces LLP, the promoter named in its MahaRERA registration.
Where is Ruparel Zinnia located?
Ruparel Zinnia is in Borivali, Mumbai (PIN 400092), Maharashtra, as declared in its RERA registration.
How many units does Ruparel Zinnia have, and how many are sold?
Ruparel Zinnia has 133 units on its RERA registration. 41 were reported sold as of July 2026, leaving 92 unsold.
How much construction of Ruparel Zinnia is complete?
By the developer's own quarterly filing, 32% of the work is done, measured against the project's cost estimate.
Is there any litigation against Ruparel Zinnia?
No litigation is declared on Ruparel Zinnia's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Borivali
- Hill View · Mumbai Suburban
- Shiv Sneh · Mumbai Suburban
- Victory Stella Nestle · Mumbai Suburban
- Hansa Residency · Mumbai Suburban
- Ipsit Deep Darshan · Mumbai Suburban
- Acres Aarambh · Mumbai Suburban
- Vardhaman · Mumbai Suburban
- Arkade Evoke · Mumbai Suburban
Other projects by Ami Modispaces LLP
- Ruparel Stardom · Mumbai Suburban